Iv-Infra prepared the designs for the planning study of the N50 between the Kampen and Kampen Zuid junctions (N50 KKZ).
This section of the N50 is considered unsafe because it has just one lane in each direction and no physical barrier separating the carriageways. The changing road layout on the N50 further increases the risk to road safety. The N50 will be widened to 2×2 lanes, significantly improving road safety and traffic flow along the route.
According to project manager Willem van der Marel, the best possible solution was devised to meet the project objectives while keeping the impact on the surrounding area to a minimum. “We prepared the designs and, in collaboration with Tauw, assessed the environmental and road safety impacts, as well as mitigation measures. We then developed the integrated design for landscape integration (IIO), incorporating these measures, including two-layer porous asphalt and noise barriers. The cost estimate was drawn up on the basis of the IIO and included all anticipated risks.”

The starting point was Rijkswaterstaat’s functional design, which was developed into a contextual design via an elementary design. The impact studies were carried out on the basis of that design. “Our strength lies in being able to move quickly between the functional requirements and preferences and their technical implementation. This allows us to respond effectively to new insights that emerge during a project. On the N50, road safety and noise led to a number of changes to the design scope.” Van der Marel looks back on an interesting process. “We found the collaboration with Rijkswaterstaat and Tauw, which was responsible for preparing the planning study, very positive. We were also able to demonstrate our strengths by completing the design for the impact studies on time. Rijkswaterstaat had set a tight deadline for the planning study itself, too. Even so, we delivered according to schedule. That is no mean feat in a process of this scale.”
Een zakelijke vraag aan TAUW | Advies- en ingenieursbureau? Get in touch
Who worked on N50
- geotechnical investigationVan Dijk geo- en milieutechniekMentioned in Extensive geotechnical investigation ahead of N50 widening
- designsIv-InfraIn this story
- functional designRijkswaterstaatIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectN50
- SubjectRoad construction
- CompanyTAUW | Consultancy and engineering firm
- CompanyIv-Infra
- CompanyRijkswaterstaat