A wide range of specialist foundation structures
Text Roel van Gils Image Joosten Concepts

First use of ‘concrete on a roll’ and a vertical reinforcement system
For five years, Joosten Concepts and Bonneveld Gewapende Grondconstructies worked as joint partners on Aanpak Ring Zuid, delivering, among other things, 130,000 m3 of EPS structures and various piled embankments and reinforced soil structures using the OLA principle. They also delivered numerous ‘specials’ due to the geotechnical complexity and integrated nature of the structures. Another notable feature is that EPS from various temporary bypasses was reused in the project, and that ‘concrete on a roll’ was used for the first time to finish several structures.

Bonneveld Gewapende Grondconstructies has been involved in Aanpak Ring Zuid since 2017. “Because of the settlement-sensitive ground, greater bearing capacity was needed at a large number of locations,” says Leon van der Heiden of Bonneveld Gewapende Grondconstructies. “EPS was chosen because of the time savings, speed and scalability. It soon became clear that the quantities involved would be enormous. That is why, from 2019, we took the project forward with Joosten Concepts, using the OLA principle.” OLA stands for design, supply and installation. “Our team of specialists supported Combinatie Herepoort with the design of the lightweight embankment, settlement-free foundation structures and various retaining walls, as well as supplying the required materials and installing them through our partner Bonneveld,” says Bob Boonzaaijer of Joosten Concepts. He and Leon take a closer look at the highlights.

Vertical reinforcement system
Aanpak Ring Zuid is divided into four clusters. EPS ground improvement was used in three of the four clusters. “Our largest sub-project was cluster 1, the N370 near Vrijheidsplein, where a temporary bypass was also built on EPS,” says Leon. “The entire EPS structure was installed in 27 phases. This staging was necessary to keep Vrijheidsplein open. EPS is ideally suited to this, because it can be used to build vertical walls. In many of these phases, the EPS therefore had to be joined to EPS structures already in place.”
Bob adds: “The Joosten Groep Vertical EPS Reinforcement System (VEW) was used to connect these vertical stages. This means an EPS structure does not have to be dismantled if extensions are needed during construction. This saves a considerable amount of time and space during installation.”

Concrete on a roll
Under the OLA principle, Joosten Concepts and its partners designed the EPS structure and prepared the installation drawings for every project phase. Other EPS structures in cluster 1 include the transition structures between the abutments and the embankment at KW-06 near the city park, and the connection to the flyover to the A7. Geogrid-anchored retaining walls were also built on EPS, making them more efficient to construct and preventing them from sliding on the structures. The bases of the aesthetic screens were founded on higher compressive-strength EPS. Reinforced soil was installed over the EPS structure in all temporary configurations to provide temporary restraint for the road structure. At several locations, the vertical walls were clad with Concrete Canvas® GCCM, effectively concrete on a roll. “Several options were considered for the finish, including geotextile and precast concrete walls, but both were quickly ruled out because of the scale, location and material costs,” says Bob. “We proposed an alternative in the form of Concrete Canvas® GCCM. It combines the flexibility of geotextile with the strength of conventional concrete, while also offering protection against UV degradation, fire resistance and vandalism. It can also be installed extremely quickly. In just two weeks, 1,200 m2 of Concrete Canvas® GCCM was installed.”

Piled embankment and foundation reinforcement
A further piled embankment with reinforced soil was built in cluster 1 at Laan van de Vrede. “This provided a settlement-free transition between the abutment and the existing embankment, to accommodate the widening of the existing structures/viaducts,” Bob explains. “Foundation reinforcement was used in every phase where the road structure was built on EPS. By distributing traffic loads more effectively through the road structure foundations, Tensar Triax geogrids allowed us to optimise the EPS grade. This delivered significant financial benefits.” Finally, a temporary traffic bypass was needed to build the N370 widening in cluster 1. “The soft ground conditions meant EPS was chosen here too,” says Leon. “Space constraints also meant we built vertical walls in EPS. In the permanent configuration, these were stepped back to form a slope with tree pits and topsoil for grass cover. We used this stepped-back approach at several locations, including Leonard Springerlaan and near the Mercure hotel. The recovered EPS was reused on the N370 for the permanent configuration.”

Carnival parades
Cluster 2 near Julianaplein is also characterised by temporary and permanent reinforced soil structures. “For the permanent configuration, we built steep walls up to 8 metres high in three phases,” says Leon. “The work was spread over several years because the area had different functions at different stages of the project.
It was also often carried out in 24-hour shifts to minimise disruption to the surrounding area.” A temporary structure was also built in cluster 2 to divert traffic, giving the joint venture room to construct the Julianaplein junction on both sides of the temporary viaduct. “A substantial amount of EPS was also used for this temporary structure, TGK-08, including to provide restraint for the road structure,” Bob continues. “The approach ramps to the temporary bridge were also built in EPS with reinforced soil. This EPS became available at the end of the project, so it could not be reused elsewhere on the scheme. Much of it was therefore donated to local carnival associations and flower parades.”

A business enquiry for Bonneveld BV? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeUnderground construction
- SubjectRoad construction
- CompanyBonneveld BV
- CompanyJoosten Groep


















