Piet Heintunnel renovation: strict schedule and unique collaboration in an alliance

Since 2005, the IJtram has also run through it, via a separate tunnel tube. The renovation is part of the ‘Aanpak Wegtunnels Amsterdam’ (AWA) programme. This programme will ensure that Amsterdam’s tunnels are ready for the future: safe to use, easy to operate and easy to maintain. We spoke to project managers Arnoud op den Kelder (municipality of Amsterdam) and Koen Beukers (Heijmans Infra/Siemens Mobility). Together, they make up the management team of the Piet Heintunnel alliance, responsible for the remaining preparation and delivery of the project.

Exemption permit in place since the new tunnel legislation came into force
On 1 May 2019, the new tunnel legislation (WARVW) came into force for existing tunnels. As the tunnel did not comply with the legislation at the time, an exemption decision was requested. A number of safety measures, including a ban on lorries in the tunnel, meant that it could remain open. “The exemption arrangement expires on 1 July 2021, which is why the renovation schedule is based on that date. This schedule gives us a clear focus on the project’s substance,” says Beukers. “To translate the vision of the Aanpak Wegtunnels programme effectively into this project, the municipality also opted for the unique collaborative structure of an alliance.”
Complex task calls for a major overhaul
The Piet Heintunnel will be fully closed to road traffic during the renovation. The IJtram will continue to run, except on a few weekends. “The fact that the IJtram also runs through the tunnel, in addition to its length, makes this a special project,” says Op den Kelder. “In 2005, the tram-tube installations were connected to the existing installations in the road tubes, dating from 1997. This adds to the complexity because some of the installations are interlinked. Some will have to be replaced while the tram continues to run. We also lack information about how some of these installations were built in the past. So we will encounter surprises during the renovation, but we want to minimise their impact. The alliance’s distinctive contract structure allows us to focus as fully as possible on the project itself and on these kinds of issues.”

Heijmans Infra/Siemens Mobility have worked together successfully before. Beukers says: “We are bringing the knowledge gained from previous tunnel renovations and new-build projects to this one. With project manager Jeffrey van Korlaar (Heijmans) focusing on delivery within the alliance, and Arnoud op den Kelder and colleagues bringing their knowledge of the municipality of Amsterdam, including at executive level, a strong synergy has developed.” Op den Kelder adds: “That is why we chose a large alliance contract, with Siemens Mobility, Heijmans and the municipality each taking responsibility for the parts of the task that play to their strengths. For Siemens Mobility and Heijmans, this includes detailed engineering and delivery. The municipality, for example, is focusing on communications and the handover to the tunnel management organisation.”
Digital technologies
Digital technologies such as BIM, Digital Twin and VR are being used on this project. The 3D BIM model forms the basis for the digital twin of the tunnel, incorporating all the new installations and the surrounding area. This will be linked to the new tunnel control software and integrated into the new control desk, from which the tunnel will be operated and monitored. “This will enable us to test the tunnel’s functional performance after renovation accurately, reduce failure costs, increase efficiency and shorten the project duration, minimising disruption for road users.” Op den Kelder says: “We have jointly recognised that the investment is worthwhile, given the huge benefits before, during and after the renovation.”

Success in challenging times
Beukers says the AWA programme’s vision of safe use, simple operation and easy maintenance is being translated into practical measures within the alliance. “This project covers the entire development, from loop to control desk. The aim is to share our results with the programme so they can be used in the other projects within AWA. That is only possible if the team works well together.” He concludes: “I’m proud of how we have brought three organisations together in an optimal way, in this dynamic environment and under the challenging circumstances of the coronavirus pandemic.”
Question about this story? Ask your question
Who worked on Piet Heintunnel
- constructionHeijmans InfraIn this story
- detailed engineeringSiemens MobilityIn this story
- mobility managersXTNTMentioned in Keeping Amsterdam accessible during the closure of the Piet Heintunnel
- energy distributionSiemens Smart InfrastructureMentioned in Busbar trunking for energy distribution at Piet Heintunnel
Keep following this
Get an email when a new story is published. No account needed.
- ProjectPiet Heintunnel
- ThemeUnderground construction
- SubjectBridge construction
- CompanyHeijmans Infra
- CompanySiemens Mobility