Fast-track binding advice: prevent protracted disputes!

Disputes during construction can seriously disrupt a project. Relationships sour, trust between the parties disappears and disputes also undermine effective collaboration. Construct Advocaten regularly sees these factors contribute to new conflicts. Before long, parties are at loggerheads while the work is still under way. Many contractors and clients will have experienced a project like this. On one thing, everyone agrees: “Never again.” The Arbitration Board for the Construction Industry has a procedure that can prevent these situations.
The need for clarity
Parties to a construction project need clarity, especially while the work is under way. For example, who is contractually responsible for the delay? Is the design fit for purpose or not? The client and contractor can have very different views on the answers to these questions, particularly when a dispute is technically complex and involves many relevant facts, with arguments to support both sides.
A snowball that keeps on rolling
If clarity is not forthcoming quickly, tensions between the parties can rise. All too often, they then take steps that only escalate the conflict. The client withholds payments, the contractor suspends the work and, before you know it, the construction contract is terminated. What may have started as a relatively minor issue has become a major dispute, with correspondingly significant financial risks. In short, there is much to be said for nipping disputes in the bud. You have to fix the holes in the roof while it is raining!

Disputes during construction can seriously disrupt a project.
Standard procedures are not enough
However, referring a dispute to a judge or arbitrator while the work is still under way does not always help the parties. Proceedings in the courts or before the Arbitration Board often take too long. By the time a judgment has been handed down, the work will usually have been completed long ago. An interim injunction proceeding, which can be brought before either the courts or the Arbitration Board, may be an option. Experience shows, however, that construction disputes are not always suited to this procedure because of their scale and technical complexity. It is not uncommon for a judgment to state that further evidence or expert investigation is required, and that an interim injunction proceeding is not the right forum for this. The parties are no further forward.
Fast-track binding advice
The Arbitration Board has recognised the importance of a swift, binding decision while work is under way. It has therefore introduced the option of Fast-track binding advice. The procedure works as follows. Each party may set out its position in writing twice, submitting all relevant supporting evidence, after which there is an oral hearing. The case is decided by one or three arbitrators with knowledge and experience in the specific area of dispute. The entire procedure, from start to decision, takes just seven weeks. The parties can also agree to tailor the procedure to their own requirements. It therefore offers maximum flexibility. The decision is binding until the work is handed over.
Unfamiliarity breeds indifference?
The advantages of Fast-track binding advice are clear. It provides ample opportunity to explain each party’s position and submit evidence, followed by a very swift decision from arbitrators with relevant expertise. How practical is it to hear from arbitrators, while work is still under way, who is right, in whole or in part? This swift decision gives the parties clarity for the duration of the project and prevents disputes from escalating.
In short, on paper this is a very welcome way of resolving disputes. Yet the procedure is not widely used. We think that is a shame. We believe it is a case of unfamiliarity breeding indifference. Readers of this article, at least, will now be familiar with it. We believe this procedure would be a welcome alternative for disputes in the civil engineering sector.
How does it work?
If this Fast-track binding advice procedure has caught your interest, it is important to know that you must agree to use this method of dispute resolution. You can do so by explicitly including the Fast-track procedure in the construction contract. If this has not been done, all is not lost. The parties can still agree to it afterwards. In short, if the parties are willing, there is nothing to prevent them from resolving disputes in this swift and practical way.
Question about this story? Ask your question
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeViable projects and strong collaboration
- SubjectBouwMat
- CompanyConstruct Advocaten