Specialist foundation works for new nuclear reactor
Text Chris Elbers/Franki GrondtechniekenImage Franki Grondtechnieken, Pallas

A unique project in the dunes of Petten
A nuclear reactor has stood in the dunes of Petten (North Holland) since the 1960s, where medical isotopes are researched and produced. However, this so-called High-Flux Reactor (HFR) is 60 years old. And with reactors of this kind, the older they get, the greater the risk that production will grind to a halt, leaving patients unable to receive diagnoses or treatment. This is why construction of the new PALLAS reactor has begun. With a range of specialist foundation works, Franki Grondtechnieken is making an important contribution to the project.
Given the nature of the work, the construction of a nuclear reactor, the entire design of the project, which began in 2021, is governed by nuclear safety considerations. This means that account has been taken of circumstances that are highly unlikely to occur simultaneously, such as extreme flooding or earthquakes. The reactor has been designed to be so robust that it will remain intact even under the most extreme conditions. This naturally translates into stringent quality requirements during construction. All aspects of the build are thoroughly prepared and extensively inspected several times to ensure that construction meets all the required standards and specifications.

Construction
Most of the work involves foundation works carried out by Franki Grondtechnieken. The Dordrecht-based company has now begun constructing the diaphragm walls that form the perimeter of the excavation pit. “This excavation pit measures approximately 50 by 50 metres and is formed by excavating diaphragm walls 1.5 metres thick and 35 metres deep,” says Jan Leen van der Vlies, Director of Construction at Franki. “The diaphragm walls are then fitted with very heavy reinforcement cages. To ensure safe handling of the heavy cages on the PALLAS site, the first ones were subjected to extensive lifting tests at the production facility in Belgium. These showed that the calculated strength and the method used to install the cages vertically could indeed be implemented safely and efficiently.”

Once the diaphragm walls are complete, Franki will install 162 drilled strand anchors in the excavation pit to ensure the stability of the excavation after digging. After the anchors have been tested and tensioned, the pit will be excavated under water to a depth of more than 20 metres below ground level. This will be followed by another impressive feat of foundation engineering. “Working from pontoons, we will install a total of 380 screwed steel tubular piles, ranging in length from 33 metres to more than 50 metres below ground level,” continues Van der Vlies. “We will then place a thick layer of underwater concrete at the bottom of the excavation. Once it has hardened, the entire pit will be pumped dry. As the final stage, BESIX Nederland will construct the permanent structural floor, 1.5 metres thick, in the pit by the end of 2024. The excavation pit can then be handed over to PALLAS.”

Challenge
The project is a very special undertaking for everyone involved. The work is being carried out in an unusual environment, which means that quality and safety are subject to particularly rigorous checks.
The project is also technically challenging. “Because the work involves extremely large foundation elements, we cannot always rely solely on experience. Quite simply, projects of this scale and type have never been carried out in the Netherlands before,” says Van der Vlies, who praises the teamwork on display. “The project’s greatest strength is the unique, open and transparent collaboration between PALLAS, BESIX and Franki Grondtechnieken, supported by the expertise and capacity of co-makers De Vries Titan (anchors, ed.) and Bonneveld (earthworks, ed.). For everyone, building a reactor is largely a new undertaking. That makes close collaboration essential. We need each other’s expertise.”
Have a business enquiry for BESIX Nederland BV? Get in touch
Who worked on it
PALLAS-reactor in Schagen
- permanent structural floor
BESIX Nederland - anchorsDe Vries Titan
- groundworks
Bonneveld - specialist foundation worksFranki Grondtechnieken
Keep following this
Get an email when a new story is published. No account needed.
- ProjectPALLAS-reactor
- ThemeUnderground construction
- SubjectUnderground infrastructure
- CompanyBESIX Nederland BV
- CompanyDe Vries Titan B.V.
- CompanyBonneveld BV
- CompanyFranki Grondtechnieken
















