The Nieuwe Mark in Breda: civil engineering at Champions League level

Text Armand Landman Beeld Jimke Joling Fotografie in opdracht van de gemeente Breda

Voor de bouwkuip wordt leeggepompt, wordt deze voorbereid met 120 meter damwand, een stempelraam tot 18 meter en 85 SI-palen.
Voor de bouwkuip wordt leeggepompt, wordt deze voorbereid met 120 meter damwand, een stempelraam tot 18 meter en 85 SI-palen.

The Nieuwe Mark is once again flowing through Breda city centre. The banks of the urban river comprise nature-friendly quays, and a new Tolbrug carries pedestrians and cyclists across the water. Main contractor FL BV (part of Reyrink Groep) completed the work in June 2025, following construction in three phases since 2022. The project combined civil engineering at Champions League level with urban logistics, nature-inclusive construction and a scope that was constantly changing. This is the story of how FL BV brought an urban river back to the heart of Breda, with green quays, a new Tolbrug and a construction team that made the difference under intense pressure.

One striking feature is the nature-inclusive quay (GreenQuays): quay walls that provide space for trees, wall plants and mosses.

“We had only just started when prices shot up because of the war in Ukraine. That immediately called for mature discussions with the client,” says Gert van Dieren, director of projects at FL BV, opening the conversation. “On top of that, many technical details changed during construction. It demanded maximum flexibility from everyone in the construction team.”

The new watercourse is much more than a cosmetic intervention: it is a complex civil engineering project, constructed in phases within a cofferdam of approximately 2,800 m², including a 60-centimetre-thick underwater concrete floor. The project used 2,125 m³ of ready-mix concrete and 2,170 tonnes of gravel, alongside 1,500 m³ of dry earthworks and 11,500 m³ of wet dredging. The cofferdam incorporated, among other things, 120 metres of sheet piling, a bracing frame up to 18 metres long and 85 screw injection piles. During the works, FL also built a temporary 15-metre pedestrian bridge to keep the city centre accessible. “Working half a metre from listed buildings, with shoppers around you and a tight window for disruption: that really is millimetre work,” says Van Dieren.

455 metres of quay wall.

Green quays

One striking feature is the nature-inclusive quay (GreenQuays): quay walls that provide space for trees, wall plants and mosses. The municipality mapped the requirements with its knowledge partners; FL translated them into buildable details, sequences and tools. The contractor developed a piece of equipment to place the substrate in a controlled way between the concrete and masonry, which was crucial for the root volume and moisture balance behind the facing wall.

Tijn Boons, work planner at FL BV: “On paper, a quay like this looks straightforward, but you only really learn when you have to get the cavity, substrate and water management right on site. We developed the details iteratively, tested them and made adjustments, always keeping safety and the historic character of the city centre in view.”

The quay structure comprised 455 metres of in-situ cast walls up to 3 metres high, a 400 m² concrete deck on piles, and a substantial masonry package: 1,550 m² of vertical masonry (approximately 233,000 bricks) plus 710 m² of horizontal masonry (approximately 58,000 bricks).   

The paving comprised 1,700 m² of asphalt, 2,800 m² of clay pavers and 1,700 m² of natural stone.

Installing sheet piles.

The Tolbrug: the most challenging part

The new Tolbrug was the most challenging element, both technically and organisationally. Its design and construction were developed by a construction team with Breda municipality and Ingenieursbureau Rotterdam, as the works were literally half a metre from a listed structure, in ground full of remnants of old bridge foundations (masonry and natural stone). Low-vibration demolition and foundation work were essential.

Van Dieren: “When you’re building so close to listed structures and lifting a bridge into place at the same time, you want to understand every detail in advance, while staying alert on site. The construction team gave us the scope to choose smart, low-vibration methods.”

60 centimetres of underwater concrete.

‘Thrown in at the deep end’

For Boons, De Nieuwe Mark was a baptism of fire. “I’d just finished my training and was immediately given a project like this. That sounds daunting, but the trust was motivating. You grow quickly when, from day one, you have to coordinate with designers, residents, suppliers and the site team.” He says the combination of urban safety, logistics (tight time windows, diversions), changing details and maintaining quality with new solutions was his most valuable learning experience.

“You learn that good work preparation isn’t a one-off document, but an ongoing process,” says Boons. “Especially with nature-inclusive quays: detail, sequence, materials, monitoring; it all interconnects.”

Concrete was cast in situ.

Collaboration

The works proceeded in three distinct phases, each with its own measures for managing the surrounding area and its own diversions. Van Dieren: “Trust was the key. Instead of becoming rigid over contractual issues whenever something changed, we sat down with the municipality and looked for a buildable option that met the project’s ambitions.”

The project is part of the municipality’s GreenQuays programme, which translates research by government bodies, the water authority, universities and nature organisations into buildable quay concepts. FL contributed detailed design, work sequencing and practical tooling (the substrate applicator) to put the research findings into practice.

Technical key facts:

Low-vibration demolition of the existing bridge deck: 50-centimetre-thick concrete floor with 15 steel HEB500 beams.
New abutments: 2 contiguous bored pile walls with a total of 32 Ø800 mm piles (alternating lengths of 6 and 14 metres), supplemented by 4 HEM360 sections and 11 HEB400 sections as reinforcement, plus 6 SI anchors per abutment.
The abutments had a 1.0 × 1.5-metre concrete ground beam and walls 4.5 metres high; built in phases.
Bridge deck: prefabricated steel, approximately 14 tonnes.    
Circular detail: use of masonry bricks that enabled 24,190 kg of material to be reused.

2,800 m² of clay pavers; 1,700 m² of natural stone.

Proud, even when the project no longer made financial sense

“In the end, we had to take a financial loss,” says Van Dieren matter-of-factly. “But when you walk along the quay today, you see why we work in this industry. The river is back, the city has gained a high-quality public space, and together we’ve built something everyone can be proud of.”

That pride is not just emotional. De Nieuwe Mark yielded practical lessons: involve the construction team early, develop details iteratively for innovative elements (such as the green quay), plan realistic urban logistics, and establish clear decision-making routes when the scope changes. Van Dieren: “We’d be happy to tender for a follow-on phase, with an even sharper plan for vibration control, monitoring and prefabrication wherever possible.”

“De Nieuwe Mark shows that innovation and buildability are not mutually exclusive,” concludes Van Dieren. “When you understand each other’s interests and keep the conversation open, you can bring a river back even in the most sensitive city-centre setting.”     

Question about this story? Ask your question

Who worked on it

De Nieuwe Mark in Breda

  1. main contractorFL BV
  2. clientBreda municipality

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectDe Nieuwe Mark
  • SubjectSpecials
  • CompanyFL BV
  • CompanyBreda municipality