The provision of information on cables and pipelines is undergoing a major transformation. This is due to the Kadaster’s new way of working. As a result, KLIC now offers a range of data access options alongside its legal framework. We spoke to Floris Konings, who represented Heijmans Infra during the Kadaster’s test phase.
First, a little background. For several years, the Kadaster has been modernising the Klic notification process to bring it in line with legislation and regulations. This process, known as KLIC-WIN, has resulted in an approach to information exchange that complies with both the Dutch WIBON Act and the European INSPIRE Directive. The transition period began on 1 January, but the entire civil engineering sector must have switched over by 1 July.
Far-reaching effects
The new approach has major implications for everyone working with information on cables and pipelines. First, network operators can now upload their cable and pipeline data to a central Kadaster database. The Kadaster can then share it quickly and efficiently with applicants. The key benefit is that the information is now supplied in vector format, making all the accompanying data much easier to use in, for example, CAD systems. This is particularly useful because the data now covers not just locations, but a range of additional information, from materials and diameters to symbols for joints and valves. The Klic notification process has changed for legal reasons, but it also brings major benefits in terms of quality and efficiency.
Quick to spot the potential
Floris Konings has already seen the benefits in practice. He is lead engineer in the Cable and Pipeline Systems department at Heijmans Infra, where the team designs cable and pipeline routes, including routes for water pipelines and district heating. He was quick to take an interest when he heard about KLIC-WIN. “We work on all kinds of cable and pipeline projects. Sometimes they’re small, standard diversions in a town, but we also work on complete cable routes for large wind farms. So we deal with a wide variety of Klic notifications. We’re also always on the lookout for ways to improve our drawings and work more efficiently.

Preparing for the guided drilling of the transport water pipeline from Loosbroek to Oss (Photo: Maikel Samuels).
So we saw the Kadaster’s new approach as an opportunity, especially when we became involved through Bouwend Nederland in the Keten AcceptatieTest for KLIC-WIN.”
The Kadaster set up the test to check whether its new approach would work in the day-to-day operations of applicants and other users. “It was a very valuable learning experience,” says Floris. “Especially because so much additional information is now made available ‘automatically’. We could see straight away that this would have to deliver a major efficiency gain. And that’s before you even consider the possibilities for BIM …”
The right software
Floris also found that software plays a major role. Heijmans Infra has long used InfraCAD, including to process Klic notifications. During the Keten AcceptatieTest, however, InfraCAD could not recognise the Klic notifications. “So the test gave us data, but we couldn’t do anything with it yet.” To test whether the data was usable, it had to be linked to the software. Floris therefore contacted CAD Accent, the supplier of InfraCAD. This brought an immediate bonus: CAD Accent had already been working for some time on a new KLIC module for InfraCAD Map, which will replace the KLIC module in InfraCAD. “We got to work together to test the new approach.”
Richer data
For around two years, Floris had had an idea of what the new approach could deliver. That idea was quickly confirmed. “What a wealth of additional data!” says Floris. “Everything is much faster, clearer, more accurate and more complete … And yet you need very few buttons and functions. With the new Klic notifications, you can do so much more.”
In the old system, ‘details’ in drawings could easily disappear. “What used to show up as a vague patch of pixels can now, as it should, actually be recognised as a valve. And five lines close together now show up as five, rather than one. Symbols and ducts are now precise, you can click through to attachments, the required precautionary measures are clearly displayed, and object data appears in handy pop-ups … Suddenly, KLIC is so much more than a legal framework. Together with InfraCAD Map, it means a huge leap in the quality of your drawings.”

Installing cables for Windpark Wieringermeer (Image: Martine Krekelaar).
Efficiency
Heijmans also found that the new Klic module makes working more efficient. You no longer have to clean up your drawings first, for example, and you can now import multiple Klic notifications in a single batch. “That might seem like a small thing to someone outside the industry, but every draughtsperson knows how frustrating it is to have to clean up a drawing. Now you can get straight to work! It saves time, which is useful during a tender, but more importantly, it makes the work so much more enjoyable.” All in all, the wait for KLIC-WIN was worth it, Floris concludes. “Together with InfraCAD Map, it really marks the start of a new era.”
Transition period: until 1 July 2019
Switching to the new vector-based cable and pipeline information represents a significant change for the entire sector. The Kadaster has therefore set a transition period. Network operators can still submit their data in the ‘traditional’ way, as raster data, until 1 July. After that, it must be submitted as vector data. From 1 July, everyone will therefore have to work with vector data only.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- SubjectSpecials