Steel made to measure for Abbegaasterkettingbrug

The bridge over the Wijmerts in the Frisian hamlet of Abbegaasterketting was refurbished in early May 2019 and fitted with a new steel deck. De Boer Staal and De Boer Snijbedrijf supplied the steel and cutting work for the new bridge deck.
A little history
The hamlet of Abbegaasterketting grew up around the ferry operator’s chain house. He ran a ferry service across the Wijmerts, charging a toll via a chain stretched across the waterway. In time, the ferry was replaced by a small swing bridge.
In 1969, this swing bridge, which was less than a metre wide, was replaced by a five-metre-wide concrete bascule bridge. The people of Abbega welcomed the new bridge, as until then they had to drive 7 km out of their way to reach the hamlet of Abbegaasterketting on the other side of the waterway.
Cutting steel and forming sections
De Boer Snijbedrijf cut the steel components for the new bridge deck to size from S355 J2+N steel with a 3.1 certificate. The steel was supplied by De Boer Staal. De Boer Snijbedrijf also formed various steel sections. These formed sections (troughs) reinforce the bridge deck and prevent it from sagging.
The steel components of the bridge deck were welded together, and the new steel deck was installed and fitted on 9 May 2019. The drive mechanism and the 21-tonne counterweight were also refurbished, and the bridge railings replaced. The Abbegaasterkettingbrug is an important link for road and water traffic in the region and, following this refurbishment, is ready for many more years of service. The motto of De Boer Staal and De Boer Snijbedrijf is: ‘YOU BUILD WE SUPPLY, also for civil engineering projects!’
Question about this story? Ask your question
Who worked on Abbegaasterkettingbrug
Keep following this
Get an email when a new story is published. No account needed.
- ProjectAbbegaasterkettingbrug
- ThemeExtending the life of roads and civil engineering structures
- SubjectSpecials