Royal HaskoningDHV deeply involved in the RijnlandRoute project

As an adviser to construction consortium COMOL5, Royal HaskoningDHV shares responsibility for the RijnlandRoute project for the Province of South Holland. Royal HaskoningDHV is closely involved in the construction project, contributing to the design, permitting and part of the construction supervision. Bart Peerdeman, COMOL5’s integrated design manager and Associate Director Infrastructure Rotterdam at Royal HaskoningDHV, talks about the company’s involvement in the project.
“Royal HaskoningDHV is involved in various disciplines related to the RijnlandRoute. These include the design of structures and the tunnel, the design of installations, and advice on matters such as ecology, soil contamination and permits. Our people work in mixed teams alongside members of the construction consortium and other consultancies. In terms of civil engineering design, we are involved in geotechnical calculations for the foundations, cofferdams, temporary dewatering and the permanent concrete structure of the tunnel and sunken road section. We are also jointly responsible for designing the flyovers at the A4. Our extensive experience in digitalisation and innovation, including parametric design, is particularly valuable for these designs. The RijnlandRoute features some highly challenging structures. These exceptional designs are precisely where Royal Haskoning excels.”
A connecting role
Peerdeman has both a technical and a connecting role in the RijnlandRoute project. “I am ultimately responsible for the integrated design. Developing an integrated design means continually looking for ways to connect. The same applies to my colleagues. I also expect them to actively build links with other disciplines within the project, both in design and delivery. This is one of Royal HaskoningDHV’s strengths, and it makes us a major contributor to the design team.”

Bart Peerdeman, COMOL5’s integrated design manager and Associate Director Infrastructure Rotterdam at Royal HaskoningDHV.
Stronger together
As design manager, Bart Peerdeman is part of the management team led by Rick Pattipeilohy (COMOL5 Project Director on behalf of Mobilis). “I am responsible for the integration and quality of the design, as well as its programme, cost control and quantities. I am also responsible for structural safety, from the design phase through to delivery. The best designs are created together. We work closely with the delivery team, making decisions together. There is often a tension between meeting stakeholders’ guidelines and requirements and what the delivery team would prefer. Finding the best possible design for all parties while keeping to the programme is a constant challenge. We make full use of the integrated digital 3D models we have created.”
A strong technical background as a foundation
Royal HaskoningDHV is known for always being able to provide skilled people who are keen to collaborate and able to do so effectively. Peerdeman says: “We have a strong technical foundation, and from there we look for solutions in all our partnerships.”
Achieving an optimal design depends on good communication and coordination with the delivery team, as well as with stakeholders and the local community. Short communication lines are essential. For the RijnlandRoute, the design team is based on site. “With your office chair in the mud on the construction site, you see more, hear more and stay more connected to the project.”
The design process does not stop when construction begins. “Although we went out on site after a year of design work, the design process is still ongoing. A design process comprises a preliminary design, a detailed design and a construction design. We are now in that final design phase,” Peerdeman explains. Most of the design work has been completed, and the large design team has been scaled back. Smaller teams are completing the design and carrying out the site engineering phase.
The end of the design process
What happens when all the designs and coordination work are complete? Peerdeman explains: “That is when my work ends and I hand everything over to the site engineer. I remain available to answer questions about the designs, but no new designs are produced. The site engineer is then on hand to answer questions about the designs that have been completed.”
A business enquiry for Haskoning? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- SubjectSpecials
- CompanyHaskoning
- CompanyMobilis