Specials

Nieuwegein, De Prinses Beatrixsluis

Nieuwegein, De Prinses Beatrixsluis

The Prinses Beatrixsluis in Nieuwegein is the largest listed inland navigation lock in the Netherlands and is located on the Lekkanaal. This canal is the main direct link between the ports of Rotterdam and Amsterdam. As more and larger vessels use the Lekkanaal, the Prinses Beatrixsluis is at risk of becoming a bottleneck. Sas van Vreeswijk has therefore been commissioned by Rijkswaterstaat to build a 3rd chamber, construct additional moorings and widen the Lekkanaal.

Prinses Beatrixsluis modernised with respect for its history

With a length of at least 276 metres and a width of 25 metres, the Prinses Beatrixsluis will accommodate vessels up to and including CEMT class Vb, with a draught of up to 4 metres. The Belgian/Dutch contractor consortium Sas van Vreeswijk has been carrying out the project since September 2016. We speak to Koenraad van Regenmortel, EPC (Engineering, Procurement & Construction) project director at Jan De Nul Group.

Samen werken aan de uitdagingen van de toekomst, dáár staat Topcon in Nederland voor.

The new chamber will be operational in February 2019.


Third chamber now fully built and finished
“Sas van Vreeswijk comprises Besix Group, RebelValley, TDP, Heijmans and Jan De Nul Group. The consortium is responsible for designing, building and financing the new chamber and widening the Lekkanaal, as well as maintaining the upgraded lock complex for 27 years. Construction began in autumn 2016 and is being carried out by Besix, Heijmans and Jan De Nul. “We are now virtually finished with construction and are completing the access to the lock,” explains Van Regenmortel. “We are also working on the industrial automation, in particular controlling the lock gates, installing all the supporting networks with a strong focus on redundancy, and developing and testing the necessary operating and safety software. The consortium’s guiding principle is to build a safe and highly reliable lock with high availability for inland shipping. That is why we are building a lock with four gates, rather than two or three. The four rolling gates were installed in August and September, together with the motors, butterfly valves and pin racks. The first software tests and tests of the actual gate controls are now under way. Everything will be CE certified before the lock opens.”

‘The Witte Huisjes’ restored to their former glory
The new chamber will be operational in February 2019. Van Regenmortel says: “Once the new chamber is open, we will renovate the old chambers one by one. The work involves completely replacing the drive mechanisms at the top of the lift towers. The old eastern protective structures will also be removed, and the existing control building, which is not part of the original listed structure, will be demolished, along with some concrete repairs. This work is due to be completed by the summer.”

The renovation plan takes the history of the Prinses Beatrixsluis into account. The lock complex includes the so-called ‘Witte Huisjes’. “These used to be staff houses for Rijkswaterstaat employees. We decided to preserve and restore them. They are now being fitted out to control the upgraded lock complex,” Van Regenmortel continues. “The new chamber has been designed as a cut in the landscape, preserving the open view of the listed lift towers of the old chambers. The complex will regain its original listed appearance.” Notably, Rijkswaterstaat awarded Sas van Vreeswijk a prize for landscape integration in recognition of its respect for the site’s history and surroundings.

Data is key tussen hardware, software en binnen alle sectoren.

The lock chamber and the northern canal.


Historic elements of the Nieuwe Hollandse Waterlinie preserved
Historic features along the Lekkanaal formed part of the Nieuwe Hollandse Waterlinie (NHW). These had to be relocated to make way for the widening of the Lekkanaal and construction of the third chamber. Van Regenmortel explains the remarkable feat carried out in 2017: “We did everything we could to move this unique military heritage intact. This was also important to avoid jeopardising the NHW’s nomination as a UNESCO World Heritage Site. With Mammoet as our subcontractor, we relocated three casemates, a small lock, a culvert headwall and a group of piles. It was a very complex operation, but a unique and highly successful one.”

Consideration for people, wildlife and the environment
To minimise disruption, the walls of the third chamber were built using diaphragm walls, a vibration-free construction method. “Whenever noise disturbance was likely, we informed local residents in advance. This was the case, for example, when installing the long sheet piles for the lock heads.”

Another challenge was to minimise disturbance to the bats’ habitat. Bat boxes are dotted around the area, and the lock complex is a crossing zone. Van Regenmortel says: “As bats are only active in the evening and at night, lighting at the lock complex could cause them considerable disturbance. To prevent this, we spent a long time searching for ‘bat-friendly lighting’ that would not drive the bats away while still providing enough light for the lock operators. We succeeded in this too.”

A ‘marriage’ lasting 27 years
The third chamber will come into service in February, after which renovation of the old locks will begin. Van Regenmortel explains: “The entire complex, including the renovated old locks, will be handed over in summer 2019. Since work began in 2016, Sas van Vreeswijk has already been responsible for maintaining the existing complex. Once the work is complete, together with Agidens and Martens en Van Oord, we will be responsible for maintaining the upgraded complex for 27 years.”  

Have a business enquiry for BESIX Nederland BV? Get in touch

Who worked on it

Prinses Beatrixsluis in Nieuwegein

  1. contractorBesix
  2. contractors' joint ventureSas van Vreeswijk
  3. contractorHeijmans
  4. contractorJan De Nul Group
  5. subcontractorMammoet

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectPrinses Beatrixsluis
  • SubjectSpecials
  • CompanyBESIX Nederland BV
  • CompanySas van Vreeswijk
  • CompanyHeijmans
  • CompanyJan De Nul Group
  • CompanyMammoet
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.