Major maintenance on national roads in the east of the Netherlands a success

In opdracht van Rijkswaterstaat heeft BAM Infra Nederland in 2021 en 2022 het integraal groot onderhoud (IGO) aan de rijkswegen in Gelderland en Overijssel mogen uitvoeren, waaronder de A50.
In opdracht van Rijkswaterstaat heeft BAM Infra Nederland in 2021 en 2022 het integraal groot onderhoud (IGO) aan de rijkswegen in Gelderland en Overijssel mogen uitvoeren, waaronder de A50.

In 2021 and 2022, BAM Infra Nederland was commissioned by Rijkswaterstaat to carry out integrated major maintenance (IGO) on national roads in Gelderland and Overijssel, including the A50. Maintenance on the A50 between the Beekbergen and Waterberg interchanges in both directions, one of the most important corridors in the east of the Netherlands, was also the most challenging sub-project. Northbound, the motorway between Arnhem and Apeldoorn was closed completely for 16 days along a 21-kilometre stretch. This was unprecedented in the Netherlands. It was a huge undertaking for BAM Infra Nederland and its partners, carried out in the middle of the 2022 construction holiday period and in tropical temperatures.

An asphalt mix containing up to 70% recycled material was used.

The IGO project involved major maintenance on key transport routes in the east of the Netherlands: the A12, A15, A50, N18, A35/N35, N36 and N48. “It is essentially the successor to the contract we also carried out for Rijkswaterstaat in 2018 and 2019,” says Robert ten Bras, business unit manager at BAM Infra Nederland, who was responsible for the tender and preparations for the 2021-2022 IGO project. The works included asphalt and structural maintenance, as well as repairs to viaducts and noise barriers. Measures were also taken to make the verges safer, including the installation of new safety barriers. “During the preparatory phase, we focused heavily on agreeing arrangements with all stakeholders and partners to ensure the safety of both road users and road workers during the works, and to limit traffic searching for routes on the local road network. This was also monitored continuously during construction, with adjustments made where necessary, and resulted in positive feedback from the surrounding area.”

The IGO project involved major maintenance on key transport routes in the east of the Netherlands: the A12, A15, A50, N18, A35/N35, N36 and N48.

Nothing but benefits

The largest sub-project within the 2021-2022 IGO project was the work on the A50 between Waterberg interchange and Beekbergen interchange, a 21-kilometre stretch. The southbound carriageway was divided into nine phases, with weekend closures, while the northbound carriageway was tackled in one go. “With a longer closure, you can get more work done in proportion and have more time to adapt or respond to any unforeseen issues. And that is reflected in the quality,” says Rense Oving, project manager at BAM Infra Nederland. “It also improves safety. We are therefore firmly in favour of closures of this kind, and Rijkswaterstaat is increasingly supporting them too. In this case, unfortunately, it was not possible to close both carriageways completely for an extended period because of the need to maintain access to the surrounding area. A longer closure in the southbound direction would have had a much greater impact on the area in spring and/or autumn because of higher traffic volumes. We therefore chose to carry out the work on this carriageway over nine weekend closures, five in spring and four in autumn.”

ADAPT Wegen

Before BAM Infra Nederland began the renewal programme, it carried out a detailed assessment of the existing assets on all national roads. “We used modern technology, including ADAPT Wegen, a tool that combines data, technology (including Artificial Intelligence) and domain expertise. A survey vehicle collects data on assets on and around the road, giving us a realistic, up-to-date picture of the condition of the pavements, structures and safety barriers,” explains Ten Bras. “This provides an important starting point for discussions and helps us begin the work without surprises.” And indeed, there were no surprises. Oving says: “The road was reopened to traffic ahead of schedule after the 16-day closure, despite the scorching heat in the summer of 2022.”

The IGO project involved major maintenance on key transport routes in the east of the Netherlands: the A12, A15, A50, N18, A35/N35, N36 and N48.

Sustainability measures

As a sustainable construction company, BAM Infra Nederland also implemented a range of sustainability measures on the IGO project, helping to make the Netherlands a better place. An asphalt mix containing up to 70% recycled material was used. “Special processing techniques enabled us to make optimum use of the planed asphalt,” says Oving. “This resulted in substantial savings in raw materials and CO2 emissions. We also used our electric asphalt paver on this project for the first time, and our asphalt paver with a hydrogen combustion engine proved its worth, as did the electric safety-barrier machine for mechanised installation of the rails, making the work more ergonomic and safer. In addition, in collaboration with Rijkswaterstaat, we laid a trial section using low-temperature asphalt (LEAB) with panacea, a plastic fibre. The aim is to validate the product for nationwide use following extensive testing.” Ten Bras adds: “This type of development is important in helping to significantly reduce asphalt production temperatures to just above 100 degrees Celsius, compared with the current 160 degrees for modified bitumen.”

Both men look back on the project with satisfaction. “It went extremely smoothly,” says Ten Bras. “Thanks also to the excellent cooperation and coordination with Rijkswaterstaat, local stakeholders and our regular partners, with whom we have delivered many Rijkswaterstaat projects over the years. This enables us to prepare a project thoroughly and work together to resolve new or unforeseen developments quickly. We have demonstrated that once again here. A real team effort.”

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectSpecials
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.