Foundations / Site investigation
Vibration-free piling, with no noise nuisance and minimal soil removal
Text Roel van Gils Image Nederfund

For projects where vibration and noise nuisance must be kept to a minimum, the grout-injected screw pile is generally an ideal foundation system. Nederfund specialises in installing these grout-injected screw piles (as well as screw injection piles) and invested heavily last year in further expanding and improving the sustainability of its plant fleet.
Nederfund began drilling grout-injected screw piles and screw injection piles in 2007. The company, based in Wijchen, is rightly entitled to call itself a specialist in this field. It has a flat organisational structure and is fortunate to have skilled staff and experienced machine operators who know their trade.
Broadly certified
Nederfund is VCA* certified and a member of the NVAF (Dutch Association of Foundation Contractors). It is also working towards certification under the Safety Culture Ladder. Nederfund is the right choice for specialist work too, such as drilling alongside railway lines or in contaminated soil. Its employees hold all the required certificates.

New rigs
Nederfund has invested heavily in its plant fleet in recent years. This means it can work in settings with limited headroom or at hard-to-reach sites, while also drilling long piles on a large scale, up to 27 metres long.
Latest emissions standards
In 2023, Nederfund commissioned a new grout-injected screw pile rig and a new concrete pump. Both machines meet the latest emissions standards and are equipped with an automated drilling data logging system. The data is used to produce drilling graphs and records, making it possible to demonstrate the quality of the work after completion.
Power pack
The grout-injected screw pile rig 4322 weighs 50 tonnes and can drill piles up to 20 metres long. Nederfund used this rig, among other things, to build the foundations for the ‘PEFA OCI Dedusting & Denoxproject’ for Tata Steel in IJmuiden. As we speak, the rig is being upgraded with a power pack, increasing its total output to 525 hp. This upgrade will enable Nederfund to reach operating speed and drilling depth even faster, further minimising emissions.
With this new rig, Nederfund now has a total of six rigs, enabling it to carry out a wide range of foundation work. And the rigs are being put to good use, with a full schedule for the coming period. Nederfund’s ambition is not only to grow steadily, but also to focus on emission-free piling. The market is not quite there yet, but developments are being closely monitored.
A business enquiry for Nederfund? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeUnderground construction
- SubjectFoundations / Site investigation
- CompanyNederfund