Foundations / Site investigation
The added value of an integrated excavation support system

Constructing an excavation support system involves far more than simply installing piles and sheet piles. Heijmans’ foundation engineering department knows this better than anyone, providing clients with a turnkey solution for the design and construction of excavation support systems. The entire system is designed and built as an integrated whole, taking account of all interfaces. A fine example is the excavation support system for Verde Vista Centrumplan in Zoeterwoude, which is currently under construction.

“Heijmans’ mission is to create a healthy living environment,” begins Paul Sleddens, business unit manager at Heijmans Civiele Specialismen. “We aim to achieve this by upholding our strategic core values: improving, working smarter and becoming more sustainable. In practice, this means designing and delivering solutions in (urban) areas safely and sustainably, while mitigating risks and investing in strong collaboration with our clients and stakeholders. We are also able to add value at an early stage and make a real difference thanks to our strong engineering team.”

Smart design
Stout is building the Verde Vista Centrumplan project in the new Meerburg district of Zoeterwoude. It comprises 150 sustainable homes, 105 private-sector rental apartments and a supermarket with a semi-sunken car park. “Stout recognises that designing and building an excavation support system requires specialist expertise,” says Sleddens. “By intelligently coordinating the design with all interfaces and risk mitigation measures at an early stage, we can often achieve significant optimisations. We have demonstrated that here too.” Peter Postma, Lead Engineer at Heijmans, adds: “For an excavation support system in an environment like this one in Zoeterwoude, cross-lot bracing is usually essential. Given the size of the excavation, 125 by 50 metres, that would pose a major challenge here. In close consultation with the client and structural engineer, we proposed an alternative.”

Safety and stability
Heijmans’ foundation engineering department designed an excavation support system without cross-lot bracing. “That means the sheet piles will deflect and press against the piles,” Postma acknowledges. “Because we joined the project at such an early stage, we were able to work with the structural engineer to optimise the pile layout so that the piles can accommodate greater deflections, allowing us to work without bracing. To limit sheet pile deflection, we decided to keep the first 5 metres on the outside of the sheet piles free of surcharge during the first phase of construction. Given the limited space, this might initially seem ‘difficult’, but it gives us extra freedom of movement when excavating the pit. This approach even allowed us to use a lighter sheet pile section. Together with the elimination of the bracing, this reduced the required tonnage of steel by 50%. We also limited noise impacts on the surrounding area and took measures to prevent damage to adjacent buildings. Finally, we always check the stability of the excavation to provide a safe, stable base for our piling and sheet piling rigs. This last aspect in particular is often underestimated.”

With its turnkey delivery of the excavation support system for Verde Vista Centrumplan in Zoeterwoude, Heijmans is clearly demonstrating its added value. “We carry out the entire excavation works, through to pouring the floor, using our own staff and equipment. Working without bracing means considerably fewer transport movements and machine relocations, and therefore lower emissions,” Sleddens stresses. “Our own drilling rigs and sheet pile machines also meet the latest requirements for sustainability and CO2 emissions. We are already preparing to electrify our fleet. At the end of this year, we will even commission an electric sheet piling rig with an 80-tonne boom crane.”
Question about this story? Ask your question
Who worked on it
Verde Vista Centrumplan in Zoeterwoude
- turnkey excavation pit constructionHeijmans
Keep following this
Get an email when a new story is published. No account needed.
- ProjectVerde Vista Centrumplan
- ThemeUnderground construction
- SubjectFoundations / Site investigation
- CompanyHeijmans