All-round foundation contractor keeps working throughout the summer

Text Roel van Gils Image Knol Akkrum

Bij Cosun Beet kwam alle expertise van Knol Akkrum samen.
Bij Cosun Beet kwam alle expertise van Knol Akkrum samen.

While half the Netherlands was enjoying the summer holidays, work at Knol Akkrum continued unabated. The all-round foundation contractor completed two impressive projects over the summer, making the most of the synergies between its different divisions: foundations, structural steelwork and concrete construction. Work at Cosun Beet is now complete, while the ArenaPoort trailer parking project is still in full swing.

Work on the ArenaPoort trailer parking project also continued unabated over the summer.

Knol brought all its expertise to bear at Cosun Beet. “The sugar factory faces a major challenge in making the plant more sustainable,” says Jappie Koopmans of Knol Akkrum. “A completely new MVR (Mechanical Vapor Recovery) installation is being built for this purpose, in a new building no less than 36 metres high. Due to material loss and the resulting reduction in thickness, the existing sheet pile wall was not strong enough to meet the design life of the new MVR installation. The existing anchor walls also lacked sufficient resistance and would in any case have been adversely affected by excavations for the basements and raft foundations of the MVR building. As a result, the quay wall had to be strengthened over a length of approximately 60 metres. Our task was to design and install the new structure from the water. All within a very tight timeframe, in the middle of the summer.”

Knol Akkrum installed the combined wall from its own pontoon using an 80-tonne crawler crane.

New quay wall

Knol first built a temporary cofferdam in the water to relieve the load on and secure the existing quay wall. “We then installed a combined wall made up of nineteen tubular piles, each 144 centimetres in diameter and 15 metres long. They weigh approximately 14 tonnes apiece and were installed from our own pontoon using our 80-tonne crawler crane. The support frames were fully prepared at our structural workshop in Akkrum. Finally, we vibrated the sheet piles into place between the tubular piles,” Koopmans explains. He adds that the combined wall was built to such a heavy specification because it is freestanding. It could not be anchored because of the newly planned foundations and the various cables and pipes behind it. After installing the combined wall, Knol Akkrum’s concrete construction division filled the piles with concrete and built the concrete capping beam, which closes the gap between the new quay wall and the old quay, which had been removed. “It is now one neat, straight quay, due to be completed on schedule in mid-October. The tight deadline is dictated by the thick juice and sugar beet campaigns.”

The 50-tonne crawler crane was used to install 340 linear metres of sheet piling.

Trailer parking

Work on the ArenaPoort trailer parking project also continued unabated over the summer. Knol Akkrum was working for Reimert Bouw & Infrastructuur on the redevelopment of the parking area for buses and lorries, just behind the Ziggo Dome. “The project also involves rerouting the bus lane,” says Koopmans. “Because of the considerable differences in level, we installed a total of 340 linear metres of sheet piling using our 50-tonne crawler crane. We then installed a total of 84 driven anchors with our piling rig for driven anchors. Everything was welded on site, using walings and heavy steel structures. We also installed the drainage outlets to restore the car park’s drainage. All in all, it was a substantial job, and we had just seven weeks to complete it, right in the middle of the school holidays.”

Both projects were highlights for Knol Akkrum over the summer holidays. And speaking of highlights, a ‘kit’ has now arrived for the 80-tonne crane used at Cosun Beet, says Koopmans. “We can now convert the machine into a PD rig and use it to drive piles approximately 30 metres long. It will be the company’s flagship machine.”     

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeUnderground construction
  • SubjectFoundations / Site investigation
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.