Five structures in the Eindhoven Noordwest area development

The Heijmans-Ploegam consortium is delivering the second phase on behalf of the municipality of Eindhoven.
The Heijmans-Ploegam consortium is delivering the second phase on behalf of the municipality of Eindhoven.

Eindhoven Noordwest is an area development focused mainly on the high-tech industry. To open up the Eindhoven Noordwest area and improve access to the city, various business parks and Eindhoven Airport, the infrastructure is being extended and upgraded. On behalf of Eindhoven municipality, Combinatie Heijmans-Ploegam is delivering the second phase. The project involves construction of the entire main infrastructure, including five structures, two of which are being designed by Ney & Partners. Ploegam was also involved in the first phase, albeit as part of a different consortium.

Phase 2 involves the construction of 4.3 kilometres of road infrastructure, including three road bridges, two cycle bridges and a number of ecological corridors, wildlife crossings and ponds for amphibians.

The Eindhoven Noordwest area development lies to the west of Eindhoven Airport. Eindhoven municipality has divided the renewed infrastructure into three phases. Phase 1, which included the construction of the iconic Tegenbosch cycle bridge, has now been completed, while phase 2 is in full swing. Phase 3 will follow at a later stage and includes, among other things, the construction of a tunnel under the A2 and N2. Heijmans and Ploegam jointly tendered for phase 2. “We know each other from previous projects and joined forces for this tender to achieve the necessary synergies,” says Joris Bevaart, project manager at Ploegam. “Our respective disciplines and areas of expertise complement each other perfectly on this project.” Heijmans is focusing mainly on the civil engineering works and asphalt, while Ploegam specialises in earthworks.

Three of the five structures are being built over the Beatrixkanaal, with the other two in open country.

Construction team approach

Phase 2 involves the construction of 4.3 kilometres of road infrastructure, including three road bridges, two cycle bridges and a number of ecological corridors, wildlife crossings and ponds for amphibians. Laurent Ney’s architectural designs from Ney & Partners were the guiding designs for one road bridge (structure 02) and one cycle bridge (structure 03). It was up to the construction consortium to make them ‘buildable’ as part of a construction team. “That was one of the reasons why Eindhoven municipality opted for an integrated contract using a construction team approach,” explains John Strik, project manager for Integrated Regional Projects at Heijmans. Bevaart adds: “Another reason was that not all the land had been acquired at the time of tendering. This allowed Eindhoven municipality to build the necessary flexibility into the schedule and construction phasing, so that compulsory land acquisition would not delay the preparation work.”

To open up the Eindhoven Noordwest area and improve access to the city, various business parks and Eindhoven Airport, the infrastructure is being extended and upgraded.

Integral viaducts

Three of the five structures are being built over the Beatrixkanaal, with the other two in open country. Strik: “The design of the structures over the canal (KW01-KW05-KW06) follows that of the existing structures: functional. The slender substructure is being cast in situ, while the superstructure uses precast beams. The two iconic structures, by contrast, are being cast entirely in situ. They are so-called integral viaducts, where the shape (an arch) is key to the structural performance. The main challenge lies in the very slender structure, with deck thicknesses of 350/400 mm and spans of between 20 and 25 metres. In addition, the large thrust forces have to be transferred from the abutments to the ground, and the interaction between forces, soil and piles requires careful consideration. The way the forces act is very different from that in a traditional structure.”

Two of the five structures are now almost complete. Structures KW03 and KW05 are still under construction, and KW06 is due to be built next year. “According to the schedule, most of phase 2 will be completed by mid-November, including the road infrastructure. Around 60,000 tonnes of asphalt will have been laid and 200,000 m3 of earth moved. The final part of phase 2 is due to follow in early 2022, including a cycle bridge over the Beatrixkanaal, for which Eindhoven municipality is now acquiring the land,” Bevaart concludes.   

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectSpecials
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.