3D reinforcement model for Prinses Alexiaviaduct

Text Roel van Gils Image Spanberg

Het maken van een 3D-model kost weliswaar tijd en energie, maar de doorlooptijd van het geheel is sneller en faalkosten in de uitvoering worden verminderd.
Het maken van een 3D-model kost weliswaar tijd en energie, maar de doorlooptijd van het geheel is sneller en faalkosten in de uitvoering worden verminderd.

Following its work on Prinses Amaliaviaduct several years ago, Spanberg is now also detailing the reinforcement for the future Prinses Alexiaviaduct on Maasvlakte 2. The 3D reinforcement model also provides the input for Spanberg’s bending machines. Spanberg is also responsible for installing the reinforcement.

Prinses Alexiaviaduct will replace the at-grade junction on Maasvlakteweg, which currently provides access to the area around Prinses Alexiahaven, and the at-grade crossing with the railway, a utilities corridor and the Container Exchange Route. The new viaduct is intended to ensure safe and smooth traffic flow to and from Alexiahaven. “We were awarded the contract on the strength of a good, long-standing working relationship with main contractor BAM, and partly because of our experience with Amaliaviaduct,” says Dennis Knaap of Spanberg. “Spanberg is responsible for producing the construction design and detailing the reinforcement in both 3D and 2D.”

Spanberg is responsible for producing the construction design and detailing the reinforcement in both 3D and 2D.

Eurocode

Prinses Amaliaviaduct has two decks, which will also be replicated in Prinses Alexiaviaduct with the same dimensions, Knaap continues. “There is, however, a fundamental difference: the new viaduct has one additional deck, making two axes. Prinses Alexiaviaduct will also have part of its deck built using precast beams, because it crosses the railway.” According to Knaap, there is little scope for synergy with the earlier viaduct, owing to changes in the Eurocode’s design assumptions. “Over the years, reinforcement has often become more closely spaced, and staggered laps are generally required. This makes prefabricating the reinforcement more difficult, including through the use of welding and spin mats (roll mats), or even impossible.”

Extensive prestressing

The 3D reinforcement model is imported automatically into Spanberg’s bending machine. “Because the machine controls production itself, human error is minimised. Creating a 3D model takes time and effort, but the overall lead time is shorter and the risk of errors during construction is reduced,” Knaap stresses. “And that is just as well, because the lead time is relatively short. Another challenge is the large amount of prestressing in the decks. When the cables are tensioned, enormous forces act on the end of the deck, requiring additional reinforcement in certain areas. These are also the critical locations where the model must be 100% clash-free.” Design and construction of Prinses Alexiaviaduct began in the third quarter of 2024, with completion scheduled for the end of 2026.     

Question about this story? Ask your question

Who worked on Prinses Alexiaviaduct

  1. main contractorBAMIn this story
  2. clientPort of RotterdamMentioned in New viaduct supports sustainable development at Alexiahaven
  3. contractorBAM Infra NederlandMentioned in New viaduct supports sustainable development at Alexiahaven
  4. block pavingWD InfraMentioned in Mechanised craftsmanship for a cycle link and block paving
  5. reinforced earth structuresVoetsMentioned in Reinforced soil structures and sustainable construction
  6. clientHavenbedrijf RotterdamMentioned in Reinforced soil structures and sustainable construction
  7. geosyntheticsHueskerMentioned in Reinforced soil structures and sustainable construction
  8. complete construction site setupBouwtech BPI BVMentioned in Low-emission construction in practice
  9. support systemSafeMentioned in Smart temporary works system for a bridge deck
  10. jointless transitionsStruktonMentioned in Jointless transitions for maximum availability and durability
  11. pile breakingVan der Jagt GroepMentioned in Pile cropping in eight phases

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectPrinses Alexiaviaduct
  • SubjectDigitalisation & software
  • CompanyBAM
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.