Collaboration at the heart of construction of Havenkwartier De Blauwe Diamant lock complex

A navigable route with a lock complex comprising a navigation lock and a flood lock is currently being built in Zeewolde to provide access to Havenkwartier De Blauwe Diamant. This is a new residential area being developed on the Wolderwijd. The primary and regional flood defences, as well as the road infrastructure, are also being upgraded. The project involves close collaboration between many different parties.
Havenkwartier De Blauwe Diamant is being developed at dike level on the Wolderwijd, one of the Veluwerandmeren lakes. To make the neighbourhood especially attractive to its new residents, Gemeente Zeewolde plans to build a marina and waterways in the form of ditches around the homes, so that a large number of houses will be situated on the water.
Primary flood defence becomes secondary defence
Because the water level in the Wolderwijd is several metres higher than in the polder to which the new De Blauwe Diamant navigable route connects, the housing development site is being raised and the primary flood defence rerouted. The navigable route will pass through the primary flood defence via a navigation lock with a 34 m chamber, a width of 6.5 m and a lift of 5.20 m. A flood lock is being built at the other end of the waterway in the future regional flood defence. Once the new primary flood defence and lock complex are complete, the existing primary flood defence will be downgraded to a secondary defence at a slightly lower level. The entire road infrastructure is also being built. This includes a road bridge over the navigation lock and a lifting bridge with a cycle path over the flood lock. The existing through-road, which will then be reserved for cycle traffic only, is being replaced by a new route around the residential area.

Strukton Civiel Noord & Oost laying a temporary asphalt surface course.
Total Cost of Ownership
As main contractor, Strukton Civiel Noord & Oost is working closely with a number of partners on the project. “Gemeente Zeewolde issued a tender at the time, which we submitted jointly with these partners and won,” says Sander Schooleman, Project Controls Manager at Strukton. “Through the tender, the client sought a sustainable, low-maintenance, future-proof system offering an optimal balance between investment and operating costs based on Total Cost of Ownership. Within the requirements set in advance for aspects including sustainability, dimensions and design, such as traditional Dutch brickwork at the locks and a red lifting bridge, we develop suitable solutions ourselves.”
Tight schedule
Construction began in September 2018, with completion planned for the end of December 2019. Most of the sheet piles are now in the ground and half of the concrete work for the navigation lock is complete. Work around the flood lock began at the end of February 2019, and the roadworks will be carried out in the coming period. The aim is to make the waterway navigable by the end of this summer.

Artist’s impression of the navigation lock.
What do the other parties involved think of the project?
Strukton Civiel Noord & Oost
Carries out the concrete work to which the waterway will connect and on which the bridge will be mounted, as well as the road construction. Senior Site Manager Edwin Eikelboom: “It’s a great project, bringing together all aspects of earthworks, road, water and concrete construction, mechanical engineering and electrical engineering. We’re building everything in dry conditions. The dike will then be opened and water will flow into the waterway. It will be spectacular!”
Heuvelman Ibis
Builds the cofferdams, including installing the steel sheet piles, and constructs the approach basins and Basalton revetment. It is also carrying out the earthworks for the new primary flood defence and downgrading the existing primary defence to a secondary defence. Project Manager Ferdi de Vries: “It’s a challenge to complete such a large project from start to finish with so many partners, in such a short time. Fortunately, the collaboration between us is excellent.”
Machinefabriek Rusthoven
Is responsible for the design, manufacture and installation of the movable steel bridges, timber lock gates, operating mechanisms and associated components such as railings, and for commissioning them. Project Manager Leo van der Bij: “Building the road bridge over the navigation lock is particularly specialist work because of its architectural design and asymmetrical bridge sections. It’s also a unique project that calls for everyone’s ingenuity.”
Van Heteren Weg- en Waterbouw
Builds the waterway, which comprises waiting areas, mooring facilities, quays and other associated amenities. Project Manager Remco Kerkhof: “It’s an ambitious project! What makes it unusual is that the new waterway is being built on the landward side of the dike, but will ultimately be on the seaward side.”
Strukton Systems, Bridges & Locks department
Is responsible for the design, preparation, execution and commissioning of the electrical control systems for the two locks and bridges. Project Manager Addie van der Bult: “What’s special is that the design is ‘home-grown’! It’s also important to keep all the different parties and disciplines involved from the outset on their toes.”
A business enquiry for Strukton Civiel? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- SubjectSpecials
- CompanyStrukton Civiel