Bridge as gateway to Parkstad

The new cycle bridge over the N274 in Schinveld, in the municipality of Beekdaelen, Limburg, opens on 20 February. Ipv Delft designed the bridge in close collaboration with artist Marijke de Goey, who created the three artworks on it. Together, the bridge and artworks mark the entrance to the Parkstad plus region.

The new bridge is part of the reconstruction of the N274 in the former municipality of Onderbanken. It provides a safe crossing for cyclists at the roundabout by Kneijkuilerweg.
Route study
The bridge design was preceded by an extensive study of alternatives. Ipv Delft worked with a task force to identify the most suitable route, taking into account factors such as landscape integration, cycling comfort and construction costs. Just under half of the 350-metre route consists of cycle path on embankments. The bridge is 188 metres long and lies in the middle of the route.

To make both the bridge and its supports as slender as possible, the entire structure was built from prestressed, cast-in-situ concrete. The bridge is divided into several large spans of 28 metres. This creates a clear, continuous appearance and leaves the space beneath the bridge free to be used as required. The long spans also preserve unobstructed views of the distinctive surrounding landscape.
Maintenance
Using cast-in-situ concrete creates a single, long, continuous bridge with no movement joints. The baluster-free railing also contributes to this: it is identical along the entire bridge and has no dominant posts. For ease of management and maintenance, the railing is made of stainless steel, which requires little maintenance and retains its appearance for a very long time. For aesthetic, budgetary and practical reasons, the entire bridge structure was treated with Keim mineral paint. This coating gives the concrete a uniform colour.

Artwork
The three artworks are integrated into the bridge design and highlight its role as a gateway. The largest artwork, made up of several stacked cubes, stands at the heart of the roundabout, on the bridge support. Thanks to close collaboration, De Lotusbloem, as the artwork is called, has been fully integrated into the bridge structure. The fixings for the cubes are therefore hidden from view.

The reconstruction of the N274 at Onderbanken was carried out by BAM Infra on behalf of the Province of Limburg. IBA Parkstad and the municipality of Beekdaelen (formerly Onderbanken) were closely involved in the project. The new cycle bridge is the defining feature of the upgraded provincial road.
Question about this story? Ask your question
Wie aan Fietsbrug over de N274 Provincie Limburg Beekdaelen werkte
Keep following this
Get an email when a new story is published. No account needed.
- ProjectFietsbrug over de N274 Provincie Limburg Beekdaelen
- ThemeExtending the life of roads and civil engineering structures
- SubjectSpecials