A new gateway to Amsterdam city centre

The public space on the city-centre side of Amsterdam Centraal is being redesigned, from the historic station building to Damrak and from the Schreierstoren to Droogbak. GEO2 Engineering BV, as a partner to main contractor Max Bögl Nederland on project De Entree, has been commissioned to develop the geotechnical design.
According to Abjan Jacobse of GEO2 Engineering BV, a key element of the redesign is to create more space in front of the station for water, pedestrians and cyclists. Beneath this ‘new’ water, there will be a cycle parking facility for no fewer than 7,000 bicycles. “We have been involved in the project since the tender stage and, together with Max Bögl, produced the winning geotechnical tender design. Our scope during the tender stage had three parts: carrying out the geotechnical calculations for the new cycle parking facility, the new Westertoegang and the repair or replacement of a number of quay walls.”

Cross-section of the future cycle parking facility. (source: wUrck)
Underwater concrete and anchors
The work began in January 2018 with the deepening of the Westertoegang. Jacobse: “The road beneath the railway tracks on the western side of Stationseiland has been lowered, giving it a little more headroom. This part of the contract has now been completed. The contractor is currently diverting and renewing cables and pipelines so that construction of the cycle parking facility can begin in 2019. We are currently developing the design into a construction design, and have to contend with many interfaces: the existing historic built environment, the listed station building and the Noord/Zuidlijn. The project will involve a substantial excavation pit, approximately 115 by 75 metres and 10 metres deep. We have opted for a traditional, robust excavation pit with underwater concrete and anchors. The cycle parking facility will be built in the dry inside it. Once construction is complete, most of the facility will ‘disappear’ underwater, allowing canal boats to pass over it.” The contractor expects construction of the cycle parking facility to take approximately five years.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- SubjectSpecials