A multidisciplinary project

A multidisciplinary project

The major maintenance works at Roode Vaart lock in Moerdijk are a perfect fit for Van der Straaten Aannemingsmaatschappij. “We can make full use of our technical knowledge and expertise on multidisciplinary contracts like these,” says head of project delivery Richard Goetheer. 

“Waterschap Brabantse Delta specified only the functional requirements in the contract, with the aim of extending the asset’s service life by thirty years. It is our job to determine how to achieve this.

The work ranges from concrete repairs and the installation of handrails and fencing to replacing the fendering and inspecting and refurbishing the lock gates. Ultimately, we must renovate and modify the lock so that a CE mark can once again be issued for the asset.”

According to Goetheer, the biggest challenge for Van der Straaten is the tight schedule. “It was particularly important to reinstall the lift gate before the storm season began (1 October). We had only six weeks to refurbish it. We carried out a visual inspection and a 3D scan of the sector gates. These gates will be refurbished at a later stage. What is impressive is that almost all the work involved was engineered in-house and carried out by our own people. That makes it all the more special.”    

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectSpecials
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.