Road construction

‘Working with the shop open’ at De Entree, in the heart of the city

TBGN 1, lassen van tramspoor.
TBGN 1, lassen van tramspoor.

The tram stops in front of Amsterdam Central Station are the beating heart of the busy passenger transport network to and from the station. This vital infrastructure artery cannot be cut off, but it does get ‘in the way’ when work needs to be carried out.

Wout Matze is Tram Infrastructure Project Manager at Max Bögl & Partners and is responsible for coordinating the urgently needed closures. We talk to him about his work and the challenges involved.

Making room for the construction pit

“To start with, the construction pit for the station is enormous,” Wout begins. “The tram tracks at the construction pit site had to be removed. We therefore applied to the municipality’s Metro and Tram department for closures, or Temporary Taking Out of Use (TBGN) periods. GVB then drew up replacement transport plans with new routes. We need the space to carry out the work, but must do so with as little disruption to passengers as possible. What does the overall scope of the work involve? Two major junctions, two large tram stabling areas in front of the station, two sets of four tracks, four stops on the west side and four on the east side. That gives you an idea of the scale of the series of TBGN periods.”

TBGN 2, laying new tram track.

Tram track past the Victoria hotel

The first TBGN was important for starting work on the construction pit. Wout explains: “To the south of the construction pit, by the Victoria hotel, we laid a new tram track in October 2019. We also renewed the entire junction at Martelaarsgracht so it could connect to the newly laid line. This gave us room to install the sheet piles for the construction pit in the space that had been cleared.”

During the second TBGN, the junction with Damrak was renewed. “This is the busiest junction for pedestrians,” Wout continues. “All the tram infrastructure there was renewed. Work then continued during the third TBGN at the west stabling area, where four platform tracks were renewed. That took place from 1 April to 1 September 2020.”

Amsterdam, work on, among other things, the underground bicycle parking facility at Central Station, TAV; Petra Zuidam Photos Richard Mouw

Pedestrian tunnel to the metro and concourse

The pedestrian tunnel was also built during the TBGN mentioned above. It runs from the construction pit to the metro and the concourse. “The tunnel will allow passengers to walk from the underground bicycle parking facility to the metro and the NS concourse without getting wet. They will then reach Central Station via the Cuyperstrap. Sheet piles have been installed in the metro link tunnel and its roof has been cast. A surcharge load was applied on the roof using large dump trucks. This means we will not have to come back later to make track adjustments after settlement. During the closures, we bring together as many construction disciplines as possible, including cables and pipes, road infrastructure, rail infrastructure, overhead lines, stops, asphalt works and underground structures. This keeps disruption from our work to a minimum for everyone.”

Latest update: TBGN 4

The fourth closure will begin in early May 2021. “It will last until October this year. We will renew the east stabling area and the track between Dam and the eastern entrance. The track on Prins Hendrikkade will also be renewed. All cables, pipes, sewer lines and gas pipes will be tackled, and Kamperbrug will be strengthened. The work also includes replacing all the overhead lines, masts, tension wires, tram tracks and points. During the first TBGN, we had all the points prefabricated and delivered by pontoon. A crane placed them on the quay, straight into position, ‘ready to go’.”

Amsterdam, work on, among other things, the underground bicycle parking facility at Central Station, TAV; Petra Zuidam Photos Richard Mouw

The final phase

Once work in the construction pit is complete, the permanent masts will be installed around it. Is there life after the De Entree project? Wout says with a laugh: “Of course, but we will always look back on a unique project, not only because of its location and the work involved, but above all because of the collaboration. We are doing this together, and that means we can all be proud of what is being delivered. As Max Bögl & Partners, we have helped bring about renewal, improvements and better accessibility, especially for disabled people. The work is enjoyable and unique, and it feels great to have been able to contribute. Together, we have delivered an excellent piece of integrated work.”     

More information: www.amsterdam.nl/deentree

De Entree at a glance: what’s going on?

Underground bicycle parking facility: structural works 

At the end of last year, underwater concrete was poured in the construction pit: around 6,400 cubic metres in just over four days and nights. The concrete floor is almost a metre thick. This sealed off the construction pit and made it possible to pump out the water. Around 52 million litres of water were pumped out in stages. The structural works could then begin. At a depth of 11 metres, the floor is now taking shape in 12 sections: first the reinforcement is installed, then the formwork is built, and finally the concrete is poured. The walls, columns and roof will follow later this year. 

Lots happening at once on Stationsplein

On the east side, preparations are well under way for the closure later this year: cables and pipes are being renewed, new paving is being laid where pedestrian routes will run around the work site, and new tram masts are being installed. Kamperbrug lies at the far end of the east side of the square. The bridge is being strengthened and refurbished, while the quay beside it, already reinforced, is now being given its finishing touches. We are laying new paving on Stationsplein, while work is also taking place on the roof of the metro hall directly beneath the square. 

Prins Hendrikkade is looking better all the time

Work to replace cables and pipes and create the new layout began at Damrak last year. Progress is good. On the building side, the service road is complete, and the final touches are now being made to the new cycle path and wider pavement as far as Kamperbrug. Work is also under way along the waterside. Later this year, the quay, tram track and carriageway will also be renewed here.

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectRoad construction
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.