Smartly installed walkway for Zaltbommel landmark

From January 2020 to March this year, a fascinating sight could be seen on the railway bridge over the River Waal near Zaltbommel. The work was carried out by Qumey Metaal of Maarssen.
Commissioned by ProRail, the family business fitted the landmark structure not only with an 860-metre walkway, but also installed 22 new electrically powered inspection trolleys beneath the bridge. Like the walkway, these facilities meet all applicable quality and safety requirements.
For around 60 years, Qumey Metaal has been a highly skilled and versatile specialist in manufacturing bespoke products and complex structures in steel, stainless steel and aluminium. This work serves clients in sectors including rail and road infrastructure with complete, tailor-made solutions. Qumey does everything it can to take the burden off its customers, from the initial design through to installation. This was once again demonstrated in the Bommelerwaard. “Over a period of 14 months, we fitted the railway bridge with a walkway using a highly innovative approach,” says Qumey project manager Roland Meijers, proudly. “This structure, weighing more than 150,000 kilos, is primarily intended for visual inspections of the track and overhead line. The walkway also serves as an escape route for train passengers in the event of an emergency.”

Installation trolley
To achieve the desired result, Qumey began digitally surveying the 11 sections of the bridge in January 2019. The results were then used to design the final walkway in an advanced 3D CAD package. Construction began in early 2020. Qumey adopted a highly innovative and clever approach to carrying out the complex work. “We wanted to minimise disruption to train services and passengers, while also avoiding the shipping channel and the floodplain, so we had to come up with a creative solution,” Meijers continues. “And that’s exactly what we did. Qumey developed a bespoke installation trolley, which we suspended from the outside of the bridge and used to build outwards. From this work platform, our fitters could complete 6 to 8 metres of walkway each day. All of this was done safely and responsibly, without disrupting rail or shipping traffic.”
Inspection trolleys
The contract also included manufacturing and installing 22 new inspection trolleys. Suspended beneath the bridge, these facilities can be accessed safely from the walkway and are equipped with, among other things, an electric drive and an escape route. “We designed, manufactured and installed the inspection trolleys in full compliance with all applicable occupational health and safety regulations and the Machinery Directive,” says Meijers. “This project once again demonstrated our extensive expertise in this field.”
A business enquiry for Qumey Metaal? Get in touch
Who worked on it
Passing path on Zaltbommel railway bridge in Zaltbommel
- metal specialist
Qumey Metaal - clientProRail
Keep following this
Get an email when a new story is published. No account needed.
- ProjectPassing path on Zaltbommel railway bridge
- SubjectRoad construction
- CompanyQumey Metaal
- CompanyProRail