Separating high- and low-frequency train services in and around Geldermalsen

Onder de naam ‘SpoorOmgeving Geldermalsen’ (SOG) werd begin 2019 het project gelanceerd om het hoog- en laagfrequent van elkaar te scheiden, in en rond Geldermalsen.
Onder de naam ‘SpoorOmgeving Geldermalsen’ (SOG) werd begin 2019 het project gelanceerd om het hoog- en laagfrequent van elkaar te scheiden, in en rond Geldermalsen.

The ‘SpoorOmgeving Geldermalsen’ (SOG) project was launched in early 2019 to separate high- and low-frequency train services in and around Geldermalsen. The contract was awarded to Mobilis and Dura Vermeer, who are working together with client ProRail under the name ‘De Lingense Alliantie’. Their work includes expanding the station yard from two to four platforms and building a third track, known as ‘De Merwede-Lingelijn’, which will run between Dordrecht and Geldermalsen. GWW Magazine speaks to Peter Boonen, senior site supervisor at Mobilis and chief site supervisor at De Lingense Alliantie.

De Lingense Alliantie has the project on track

Peter Boonen: “Working within an alliance is different”. Photo: Bouwfotografe.

Around 80% complete in December

“Construction began in early 2019,” Peter begins. “Five railway possessions have been scheduled for the entire project. During the summer 2020 possession, the entire station yard was rebuilt in around 700 hours, over a six-week possession. Train services were disrupted as little as possible during this period. From then on, the focus shifted to a seven-day possession, which took place last summer, in 2021. The third track, the Merwede-Lingelijn, has now been connected and brought into service. Geldermalsen therefore now has three tracks approaching from the north.”

Trains no longer need to use a set of points, but can travel on their own track towards Geldermalsen station. “Over the past year, we have prepared the platforms for this expansion,” Peter continues. “The canopy above the platforms has been prepared, and a new passenger subway has been brought into use at the station. The old footbridges have been removed. We expect to have completed around 80% of the project by December 2021.”

The tight schedule also means working evenings and nights. Photo: Bouwfotografe.

Civil engineering and rail works split

Within the alliance, responsibilities are clearly divided. TBI company Mobilis is responsible for the civil engineering works. These include widening the railway corridor to accommodate the third track, building three underpasses and a third railway bridge over the Linge, constructing the passenger subway beneath the station and building the new platform canopies. Dura Vermeer Rail is responsible for laying the track and installing railway cables and services. “A lot of track was removed last summer, and the lines were prepared for the possession so they could be brought back into service last summer,” Peter explains. “To move the largest tunnel, the road and cycle tunnel, into place, we excavated a ramp. The tunnel itself was assembled in the neighbouring fields and transported to its destination via the ring road.”

Over the past year, the canopy above the platforms has been prepared and a new passenger subway has been brought into use at the station. (Image: Daisy Komen)

Balancing workloads and safe working

Peter cites finding a balance between workload, which is always high during railway possessions, and working safely, particularly where passengers are concerned, as one of the biggest challenges. “Safety comes first. But to meet the workload, we have to plan the work in smart stages. We also need to be able to work ahead, so that we have some room left during the seven-day possession. During that possession, we focused on work that could only be done in that time window.”

“Working within an alliance is different,” Peter emphasises. “ProRail is also part of the design team. Risks are shared and the budget is managed jointly. The challenge within the alliance is to put the interests of the alliance ahead of those of the individual parties. We have succeeded in doing that.” We ask what happens next. “The noise barriers were installed last summer, so we can now carry out work outside them without disrupting train services. This includes building the Nieuwsteeg underpass, including its access ramps and stairways. We will also complete the station, mainly with finishing work. This includes tiling, LED light strips, ceilings and paving. Alongside the track, we are building emergency and escape routes and installing fencing.”

When most of the project is completed in December, Geldermalsen station will be fit for the future. Thanks to smart planning, efficient working and good communication within the alliance, everyone can look back with satisfaction on a project that caused as little disruption as possible.     

Have a business enquiry for Mobilis? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectRoad construction