Renewing platforms is a fine example of logistical expertise

Renewing an entire platform in 52 hours, with work continuing 24/7. To put it mildly, that is a major logistical challenge: a demanding operation requiring a great deal of work in a short time without compromising on quality. Van Ooijen Gouda is tasked with delivering projects like these on behalf of rail infrastructure manager ProRail and in collaboration with fellow contractors.
A complete platform in 52 hours

When asked which rail project had been a real challenge over the past year, Harmen Eijkelenboom, managing director of Van Ooijen Gouda, does not have to think for long. “As part of the Perrons op Norm programme, we worked on three stations on the same rail route at the same time last year: Rhenen, Veenendaal-Centrum and Veenendaal-West. Working in a station environment is not easy. As a contractor, you are often restricted to the periods when ProRail closes the railway for engineering work, and have to take account of all the timetables and logistical operations at the stations. We had nine consecutive days of work, 24 hours a day, to renew these three stations. The job had to be completed within that time, as the stations could only be closed for that long.” These stations are just three of the 300 stations whose platforms ProRail has rebuilt in recent years. “This work is covered by the Perron Op Norm contract (PON contract). On behalf of ProRail, we build and rebuild sand and sleeper platforms at railway stations to the P76 standard. We make platforms exactly 760 millimetres high, measured from the top of the rail. We also ensure that the distance between the platform edge and the centre of the track is exactly 1,700 millimetres. This gives passengers with reduced mobility better access to trains, by ensuring that every platform is at exactly the same height and distance from the track.” Van Ooijen carries out this work with three fellow contractors.

Keeping platforms at the right height
The P76 standard has been in force since 2008. Around 300 of the Netherlands’ more than 400 stations, with a total of around 1,000 platforms, have now been rebuilt. Given that the P76 standard was introduced in 2008 and has been in force for almost 15 years, some platforms no longer comply with it. This is simply because they have subsided, for example, or because track levels have been adjusted over time as a result of maintenance. This means the platforms need to be adjusted again. “We have a Beheer Toegankelijke Instap contract (BTI contract) with ProRail for this work. This means we ensure that platforms remain at the correct height. We are the only contractor carrying out this work on behalf of ProRail across the country’s four regions.”

The most circular platform tile
Wherever possible, platform alterations and maintenance must be carried out sustainably. One of the sustainable measures is to use the most circular platform tile currently available in the Netherlands. The tile was developed by De Hamer, a company based in Nijmegen. “It is made from 86 per cent reclaimed platform tiles. In 2021, we became the first company in the Netherlands to use these tiles, covering around 10,000 m2. The tiles were installed mechanically from the track using our newly developed, specially designed vacuum clamps. We are also the first company to install the safety line marking entirely by machine. It is sustainable, circular, fully compliant with occupational health and safety requirements, and fast. In fact, we now carry out all our projects using this mechanised approach. We also install the most sustainable retaining walls, in partnership with two other contractors. The walls are manufactured at the Bosch Beton factory in Barneveld. Whereas retaining walls used to be 1 metre long, Bosch Beton now makes them in 2-metre lengths. This makes manufacturing more sustainable, and installation faster and therefore more sustainable too.”
Renewing cycle parking facilities
Van Ooijen Gouda specialises in delivering safe road and rail infrastructure. Its work at and around stations therefore goes beyond simply renewing platforms. Van Ooijen also focuses on improving track sections, building cycle parking facilities and constructing service paths. For example, the company holds the contract for cycle parking facilities across the Netherlands. “More and more people are cycling to the station. As a result, many smaller stations do not have enough good-quality cycle parking. We build new facilities across the Netherlands wherever there is a shortage. The client does not need to worry about a thing, as we also lay the paving and provide the cabling, lighting and signage. We take care of everything needed to expand the cycle parking facilities.”
100 kilometres of inspection path
After summer 2022, Van Ooijen has another major project lined up: renewing the inspection paths along the Amsterdam-Utrecht railway, in collaboration with the Reimert Groep. These paths have a total length of 100 kilometres. “We do virtually everything involved in maintaining and renewing stations. As well as civil engineering work, we also carry out building work on various buildings owned by the rail infrastructure manager on behalf of ProRail. For example, we will replace the roofing on the canopies at Barendrecht and Schiedam stations.”
Step 4 on the Safety Culture Ladder
Alongside its ambitious sustainability goals, safe working is Van Ooijen’s number one priority. “Our people work every day around large machines, alongside roads and railways, and carry out physically demanding work. This brings a number of safety risks. Earlier this year, we organised a special Safety Day. It is one of the ways we keep our people informed. A range of topics are covered, including risk assessment and safety protocols. At the Safety Day, we launched our new SAVE safety campaign. SAVE stands for Samen Alert, Veiligheid Eerst, meaning ‘Stay Alert Together, Safety First’. We have put the new logo and safety mark on all our workwear and site hoardings. This helps us keep our people’s safety awareness high.” Proof that Van Ooijen takes safety very seriously came in March this year, when it achieved Step 4 on the Safety Culture Ladder. “A great step forward for our company, and confirmation that safety is a top priority for us!”
Question about this story? Ask your question
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeMaterials and techniques for infrastructure
- SubjectRoad construction
- CompanyBosch Beton