Innovative, zero-emission noise barrier completed alongside the A28
Text and images Holland Scherm

Along the A28 near Harderwijk, Holland Scherm has built a future-proof noise barrier that significantly reduces traffic emissions and noise nuisance for local residents. The project, delivered under a UAV-GC contract, is characterised by sustainable material choices, innovative technology and a fully emission-free construction method.
Design & contract form
In collaboration with the municipality of Harderwijk, room was created within the framework for several innovations. The design was conceived with a clear ambition: a barrier that not only reduces noise effectively, but also lasts for many years thanks to sustainable materials and smart technologies.

Civil engineering works and foundations
“We carried out extensive civil engineering works and extended the earth embankment using electric machinery,” says Holland Scherm project manager Edwin Dening. “All earthworks were carried out emission-free. The foundation profiles were also installed using an electric crane and vibratory hammer, ensuring the heavy elements were positioned accurately and sustainably.”
Structure & materials
The steel frames were supplied with strength and service life in mind. The concrete panels were manufactured with basalt fibre reinforcement to create lighter, more sustainable panels. The glass panels used ensured that light and views were preserved for the surrounding area.
Innovation
An aerodynamic module was installed on top of the barrier, using airflow to further reduce noise. “This technology meant the barrier could be built 2 metres lower without compromising performance,” explains Dening.

Sustainability & collaboration
Installation was carried out using a special clamp mounted on an emission-free crane. “The entire project was delivered using electric machinery, reducing CO2 and nitrogen emissions to zero. Thanks to close collaboration and rigorous project management, the work progressed smoothly and predictably,” says Dening in retrospect.
Completion
At the handover, project manager Jan-Willem Roos of the municipality of Harderwijk emphasised that the client and contractor had worked together optimally within the UAV-GC framework. “The result is an innovative, sustainable product that meets all requirements and expectations.” The new noise barrier alongside the A28 is a prime example of modern, sustainable infrastructure. With effective noise reduction, high-quality materials and emission-free construction, the project contributes to a better living environment and demonstrates that zero-emission construction is achievable on a large scale.
Question about this story? Ask your question
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeMaterials and techniques for infrastructure
- SubjectRoad construction
- CompanyRoos Groep