Foundations of reinforced soil
Text Roel van Gils Beeld Voets Gewapende Grondconstructies

Sustainable and cost-efficient
In early spring 2023, Voets Gewapende Grondconstructies joined Boskalis’s tender team to develop an integrated, viable design for widening the A2. It soon became clear that the project was particularly well suited to the design and construction of civil engineering structures on reinforced soil foundations. In addition to its sustainability benefits, this approach offers significant advantages in terms of construction speed and cost efficiency.
As well as the technical design, the overall solution also presents various challenges in terms of phasing, explains Gino Jongmans, managing director at Voets Gewapende Grondconstructies. “To bridge the difference in height between the new construction and the existing motorway, several temporary reinforced soil walls are also being designed.”

Expanded scope
Voets Gewapende Grondconstructies’ scope covers the foundations for five structures on the A2, five structures spanning the A2 and eight retaining structures running parallel to the A2 as part of the widening works, says Constant Brok, design lead and geotechnical specialist at Voets Gewapende Grondconstructies. During the project, the scope was expanded to include four additional wildlife crossings. “As part of a small design-and-build team, we investigated the best foundation solution for the abutments. Reinforced soil was also the most logical choice here, consistent with the foundations of the other structures,” says Jongmans.

Unique connections
The visual quality plan requires a high standard of finish, particularly for the use of gabions. “At Voets, we have developed unique connections for attaching both gabions and concrete panels to the reinforced soil,” explains Brok.
PVA grids
Together with the main contractor, it was decided to design all reinforced soil structures using polyvinyl alcohol (PVA) as the base material instead of polyester. Jongmans says: “This removes the strict requirements for the pH values of the fill material and also offers design and construction benefits for both the subcontractor and the main contractor.”

Construction
According to Jongmans, delivering this project requires considerable flexibility from the organisation. “Work began in phases and is being carried out in changing conditions, sometimes at night and at weekends. With two production teams and a compact design team, we are constantly adapting to the schedule and progress to deliver the planned volumes. And this is all happening in a very positive partnership with the people at Boskalis.”
Een zakelijke vraag aan Voets Gewapende Grondconstructies B.V.? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- SubjectRoad construction
- CompanyVoets Gewapende Grondconstructies B.V.
- CompanyBoskalis Nederland