First: a platform paving slab that is kinder to pavers

Susteren station is being renewed in phases. A completely new paved surface on both platforms is part of the large-scale upgrade. It is the first station in the Netherlands to be fully paved with a new platform slab designed to be kinder to pavers. The first phase has now been completed. Time to look back with Arjan Beens, project manager for principal contractor Knipscheer Rail-Infra.
Susteren station is undergoing a major transformation. Knipscheer is replacing the benches, bins, waiting shelters and information boards. The public address system, station clocks and lighting on the platform and forecourt are also being renewed. The most substantial task, however, is the renewal of both side platforms. Beens says: “The retaining walls, stairways and paving are all being replaced. The platform is also being widened and the ramps adapted. The two side platforms are being renewed in two phases, during two 48-hour possessions. Phase 1 was successfully completed over the weekend of 6 and 7 April.”

The new slab is made from recycled concrete and is much lighter than a standard slab.
45,000 kilograms less to lift
During the 48-hour possession, Knipscheer had only one track available. “In the three weeks before the possession, we set up the worksite and carried out preparatory activities wherever possible, including soil remediation on the platform,” Beens explains. “As we had only one track available, the other was being used by ProRail for other work, the logistics plan had to be accurate to the minute. Within 48 hours, we installed new retaining walls along a 200-metre stretch and replaced all the paving. For the first time in the Netherlands, a new platform slab designed to be kinder to pavers was used. It is made from recycled concrete and is much lighter than a standard slab. Thanks to this slab, our pavers have 45,000 kilograms less to lift across the station.”
Around fifty Knipscheer Rail-Infra employees worked around the clock during the possession to carry out the work. “Passengers who watched in amazement could hardly believe that so much work had been done in one weekend,” says Beens. “We too are pleased with how phase one went. Later this year, in week 47, the other platform will also be renewed.