Exploratory study into improving cyclist safety on the Ziendeweg

Close the road to through motor traffic or build a segregated cycle path. What is the best way to improve cyclist safety on the Ziendeweg?
What routes and solutions are possible in this distinctive yet complex setting? The Ziendeweg is a long, narrow road that sees heavy traffic at certain times. Many motorists use it as an alternative to the provincial roads.
The road provides access to agricultural plots. It also carries a high volume of cycle traffic for journeys to school and work, as well as recreational use. Overall, the combination of the road’s length and limited width, together with the different traffic flows, is far from ideal and compromises road safety. Commissioned by the Municipality of Alphen aan den Rijn, Iv-Infra conducted an exploratory study into how best to improve the traffic situation for cyclists.
The Ziendeweg
The Ziendeweg is a narrow road approximately 3.5 km long. As well as linking Zwammerdam and Nieuwkoop, it provides a route to Bodegraven, the A12 and the N231 towards Uithoorn. For cyclists, it is the only route between Zwammerdam and Nieuwkoop that does not involve a detour. It is also an important recreational route (Groene Hart, Nieuwkoopse plassen) and part of the Fietsknooppuntennetwerk.

A crown jewel with challenges
The area around the Ziendeweg is unique: it is the only place in the world where a polder is drained by a working series of windmills without mechanical assistance. Other distinctive features of the area include its high landscape and archaeological value, its ecology and its many culturally and historically significant features. The area is regarded as a crown jewel of the province, which also brings challenges. The general management guideline for crown jewels is to preserve their exceptional quality. This guideline sets out how the province intends, in principle, to approach developments in terms of cultural heritage and spatial quality. Here, cultural heritage is the key driver of spatial development. The Ziendeweg has therefore remained much as it is for almost 800 years.
A complex puzzle
The limited space and the different traffic flows make the area complex. Projects in the surrounding area that could affect this project also present a challenge. For example, the Rijnland Water Board is planning a dike reinforcement project on a dike bordering the Ziendeweg. The solution ultimately selected must therefore not obstruct the dike reinforcement works.
Because space is limited, any changes will affect the surrounding area. The road is only three metres wide and has numerous passing bays, which severely limits the options for change. In addition, the land is privately owned. Balancing all the interests is therefore a complex puzzle. To develop a solution with broad support, landowners and other stakeholders have been involved from the earliest stages of the project. However, because the coronavirus pandemic had just broken out when the project began, this took a different form from the usual approach.
Different options
Iv-Infra was asked to identify what could be done to provide a segregated cycle path and what changes could be made to the road itself. At the start of the exploratory study, several routes worthy of further investigation were developed into outline designs. Broadly, these were a segregated cycle path through the polder, a segregated cycle path alongside the Ziendeweg (east and west), and measures to improve safety on the Ziendeweg itself. The alternatives were compared on the basis of, among other things, their spatial and environmental impacts, stakeholder interests (landowners, local residents and interest groups) and costs. The exploratory study took an integrated approach to ensure that the outcome would be a solution that both improves cycle safety and has the support of landowners and other stakeholders, while also fitting seamlessly into the distinctive setting and minimising its impact on the area. The routes were therefore assessed from more than just a civil engineering perspective.
An environmental scan was carried out during the exploratory phase to identify all the factors that could influence, and therefore affect the feasibility of, a route. These included archaeology and cultural heritage, soil and water (hydrology), ecology, spatial planning, cables and pipelines, traffic, and recreation and tourism. Discussions with landowners and stakeholders also formed part of this assessment.

Involving stakeholders
Due to the coronavirus restrictions, the different routes could not be presented to landowners and stakeholders at a conventional public meeting. Instead, individual discussions were held around kitchen tables. These discussions clarified stakeholders’ views on the options. The views were then translated into a matrix of support indicators, showing how landowners and residents felt about particular options. Finally, all the information from the environmental scan and the kitchen-table discussions was assessed using a decision-making model.
Cycle path or road closure?
It soon became clear that a segregated cycle path through an open area was not realistic. The best location is close to the road, as this follows the existing infrastructure as much as possible and requires the fewest changes to the surrounding area. As for options on the Ziendeweg itself, the only measure that would offer any additional benefit is to close it to motor traffic, allowing access only for destination traffic and agricultural vehicles.
Iv-Infra is currently developing the cycle path design further, while discussions with neighbouring municipalities are under way to assess the implications of closing the Ziendeweg to motor traffic. The municipal executive has stated that it currently prefers to close the Ziendeweg. However, this option still needs to be properly investigated, as closing the road would affect residents and other roads. The results will be presented to the council this summer, which will decide whether to build a segregated cycle path or close the road to motor traffic.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- SubjectRoad construction