Comprehensive in rail engineering and supply

When you need a reliable partner for a major, complex project such as De Entree in Amsterdam, to take care of rerouting the tram line, who do you bring on board? Alom from Arkel, of course.
Edwin Aerts’s company specialises in the engineering and supply of rail materials. The name Alom is no coincidence: it reflects the company’s comprehensive capabilities.
We spoke to Edwin Aerts, CEO of Alom, about the work in Amsterdam. “Our company supplied the necessary points, crossings, straight and curved track sections, and rail fastening systems,” he begins.

Tram infrastructure redesigned
The plans to redevelop the area around the central station also required the tram line to be rerouted. “The tram infrastructure was redesigned and its layout reconfigured. This time, we didn’t have to go back to the drawing board ourselves, as we were given the design,” Aerts explains. “The challenge was the all-encompassing nature of the work, which was right up our street. All the materials had to be delivered ‘in time’. That called for tight planning and a great deal of checking on our part, as our points supplier is based in the Czech Republic and transport was sometimes disrupted by COVID. Another of our partners carries out the rail bending and milling for us. It was quite a job getting everything there and then delivering it to the site in Amsterdam on time.”
A reciprocal partnership
One of the measures taken by Max Bögl & Partners to enable work on site was to divert the tram service. Work could then begin on the new tram line, using the components supplied by Alom. Aerts is impressed by the way the companies worked together: “This project demands so much flexibility and commitment from the companies involved that it can only succeed if everyone works in perfect harmony. Max Bögl really treated us as a partner, and I can say that the partnership was entirely reciprocal. It’s been a great working relationship.”

Sustainable logistics
Alom acted as a supplier, delivering the necessary components exactly where they were needed. “That’s sustainable logistics: it prevented errors and saved the contractor processing our materials a great deal of time. To top it all, in line with the ‘less disruption’ approach, we delivered everything without packaging, in plastic crates sorted into components for each length of track. This meant that workers could take all the relevant materials straight from the crate at the work site and stack the empty crates easily.”
No missing materials, no mistakes
Why do you think Max Bögl chose Alom? Aerts replies: “We were included in the tender because we excel at providing a comprehensive service. Everything we supply is compatible, fits precisely and is complete. During the preliminary phase, we carry out continuous co-engineering with the client, with the aim of ultimately delivering everything as a tangible solution. This takes care of the rail element of the project. No one is left short of materials and there are no mistakes.”
Max Bögl & Partners, the municipality of Amsterdam and GVB were responsible for the design that was provided. “A very well-executed design,” Aerts concludes. “That’s characteristic of the whole process at De Entree.”