Alkmaar Noord station: more accessible and highly sustainable

ProRail aims to ensure that everyone can travel by train independently, including people with reduced mobility. To achieve this, all railway stations in the Netherlands must be made fully accessible and easy to reach.
With that aim in mind, the railway infrastructure manager began upgrading nine stations in 2015, working with NS and K_Dekker bouw & infra, among others. Alkmaar Noord station, which is more than 40 years old, is currently undergoing a major overhaul. When the work is completed as planned this summer, the station will have been given a complete makeover, with sustainability at its heart.
ProRail wants to make train travel in the Netherlands as easy as possible for as many people as possible. “To make stations accessible for passengers with a disability, for example, we are building step-free platforms and installing handrails with braille information,” says Lieke Rubers, a station project manager at ProRail. “By 2022, at least 90 per cent of passengers should be able to find their way around stations without assistance. Our target is 2030. By then, all NS stations should be independently accessible to everyone.”

A nod to Alkmaar’s main station
One of them, the severely outdated Alkmaar Noord station, is undergoing a major upgrade until the middle of this year. In fact, the railway station, located on the Amsterdam Centraal-Den Helder and Alkmaar-Hoorn routes, is being completely rebuilt after being demolished in its entirety. The work is being carried out to designs by Amsterdam-based architectural practice VenhoevenCS, which previously designed Alkmaar’s Centraal Station. The reference to that earlier project is unmistakable, says Rubers. “The design of Alkmaar Noord station is based on Alkmaar’s main station. You can see this, for example, in the choice of materials and colours. The result will be a modern railway station that is fully accessible to every passenger.” To achieve this, new stairs, ramps and two glass lifts will improve access to the platforms. The station building and the pedestrian subway will also have an open, transparent feel. Generous platform canopies will be built, with glass waiting areas beneath them, offering passengers greater comfort and shelter. New furniture will also be installed, and the subway beneath the tracks will be thoroughly refurbished.
Sustainability high on the agenda
Sustainability is a top priority for ProRail, as is once again evident from the Alkmaar Noord project, which is receiving a (financial) contribution from the Municipality of Alkmaar. “As well as energy-efficient LED lighting in the station building and pedestrian subways, 170 solar panels are being installed on the roof. They will generate more than 90 per cent of the energy required,” says Esther Versteegh, construction manager at ProRail. “That will make the station building virtually energy-neutral. In addition, a large proportion of both the construction and demolition waste and the existing materials will be reused. The residual materials that are not suitable for reuse after sorting will be processed at a waste-to-energy plant. The heat generated will be used to heat schools, greenhouses and residential areas.”

Collaboration within the three-way partnership runs smoothly
ProRail is very enthusiastic about its collaboration with contractor K_Dekker bouw & infra and the other construction team partners and stakeholders. “We have been working together for several years to improve station accessibility,” says Versteegh. “So we know each other well and know what to expect from one another. This project has shown that once again. We challenged K_Dekker to come up with a proposal that fully addressed our objectives and ambitions. Once again, they delivered. The partnership is growing stronger, thanks in part to Antea. This consultancy and engineering firm not only reviews the structural designs and supervises the works, it also acts as an adviser and sounding board for us. In short, collaboration within the three-way partnership between K_Dekker, Antea and ProRail is running smoothly. And another important point is that all three of us learn from each other every day. That is greatly benefiting the project and its outcome.”
A varied project
The construction work currently being carried out by K_Dekker bouw & infra in Alkmaar fits perfectly with the diverse order book of this forward-looking, multidisciplinary specialist. Under the contract signed with ProRail in 2015, the company, which operates from Warmenhuizen and Amsterdam, is ensuring that train passengers in the city of cheese can access the station and platforms without difficulty. Rick Bleeker is K_Dekker’s project manager. “ProRail’s brief was clear,” he recalls. “They wanted not only an accessible station, but also a building with a clean, open character. We were able to meet those requirements in full, both in the design and in the construction. There was also a strong emphasis on sustainability, including reusing as much of the existing material and demolition waste as possible. We have done an excellent job of that too.”

Prefabrication
Clients can confidently leave it to K_Dekker bouw & infra to translate an architectural design creatively into an efficient construction process and a buildable, sustainable result.
The company’s versatility, extensive capacity for innovation and craftsmanship provide a solid foundation for this. These qualities are closely linked to its core values: togetherness, success, progressiveness, inspiration and pride. K_Dekker bouw & infra has once again excelled on the Alkmaar Noord station project, which brings together both building and civil engineering disciplines. “Together with our partners, we looked at how to carry out the work as quickly and efficiently as possible, with minimal disruption to the surrounding area and rail traffic,” says Bleeker. “That approach led us, for example, to prefabricate all four canopies, each measuring 22 by 8 metres, in close consultation with the Municipality of Alkmaar, in the car park next to the station. They come fully equipped: steelwork, folded metal panels, timber slats, security cameras and lighting. In short, they are fully finished. We also opted for off-site prefabrication of the lift pits. To do this, we built a concrete factory specifically for this project at our yard in Krabbendam, a 15-minute drive from Alkmaar.”
A successful partnership
Although the entire construction project spans almost a full year, smart off-site prefabrication of the canopies and pre-planned track possessions mean that the physical works will take only around 20 weeks. The high point was the installation of the platform canopy, a milestone completed at the end of March. However, the relatively short construction period did not mean that building the station was without challenges for K_Dekker. Quite the contrary. “During demolition, the installation of sheet piles for the lift pits and the assembly of the canopies, no trains could run through the station and a pre-arranged possession was in place. This meant we had to complete the work in a very short period, which created considerable time pressure. But we got it all done in good order,” says a proud Bleeker. “The excellent collaboration with ProRail and the Municipality of Alkmaar, as well as the mutual trust, certainly contributed to that.”
Curious about progress on the Alkmaar Noord station project? Follow the livestream at https://live.netcamviewer.nl/ProRail-Station-Alkmaar-Noord/1161
The versatile builder
Building comes naturally to K_Dekker bouw & infra. A can-do attitude has been in the company’s DNA since it was founded in 1963. These qualities are evident in every project delivered by the company, which operates from Warmenhuizen and Amsterdam. K_Dekker can rightly call itself ‘the versatile builder’. By combining a drive for innovation and craftsmanship with a no-nonsense work ethic and a healthy dose of creativity, this construction and infrastructure specialist continues to surprise with outstanding projects. Results that fill both its clients and K_Dekker’s own professionals with pride.
Question about this story? Ask your question
Who worked on it
Alkmaar Noord station in Alkmaar
- site managerK_Dekker bouw & infra
- architectVenhoevenCS
- adviserAntea
- clientProRail
Keep following this
Get an email when a new story is published. No account needed.
- ProjectAlkmaar Noord station
- SubjectRoad construction
- CompanyK_Dekker bouw & infra
- CompanyVenhoevenCS
- CompanyAntea
- CompanyProRail