Road construction

A9: A project of big numbers for Van Schaik Grondverzet

Text Suzanne van Gaale Beeld Van Schaik Grondverzet

Crawler cranes were used for the earthworks.
Crawler cranes were used for the earthworks.

From complete water management and reinforced soil to pile-supported platforms and retaining walls. To put it mildly, the range of work Van Schaik Grondverzet is carrying out on the widening and deepening of the A9 is extensive. Director Peter van Schaik: “Over the past four years, I’ve often thought, ‘This is Mission Impossible’, but our team always manages to pull it off. That makes me really proud.” 

Trench shoring at the A9.

Van Schaik Grondverzet is often called in for specialist earthworks on major infrastructure projects. That is also the case with the widening and deepening of the A9, where VeenIX is responsible for the project on behalf of Rijkswaterstaat. It started with a request to see whether Van Schaik could lay a section of sewer. Four years on, Van Schaik has completed an impressive list of assignments. “We’re working along the entire route,” says Peter van Schaik, the second generation of the Van Schaik family to run the company. His father founded the business 55 years ago. Today, it specialises in earthworks in the broadest sense of the word. It has a large fleet of machinery and its own skilled staff, from work planners to GPS specialists. “The work on the A9 is a very challenging assignment for us, with a huge amount of variety. At Amstelveen, the A9 will run in a cutting for 1.6 kilometres. We spent the first two years working on the bypass. We carried out earthworks for the temporary bridges and managed the entire water system, installing 5 kilometres of pipework. We do all of this in-house.” 

Van Schaik brings in extra equipment for weekend works.

Lightweight

To build the bypass, Van Schaik constructed a large number of piling platforms for the piling and sheet-piling works. This involved moving around 100,000 cubic metres of earth to ensure the platforms were level. “We also placed around 90,000 cubic metres of Argex expanded clay aggregate as fill. It is a lightweight clay aggregate, making it ideal for the soft ground at Amstelveen. But because it is so light, it is also quite challenging to place. We bought a lightweight bulldozer specifically so it could drive over the material.” And that is not all: the earthworks specialist has also been supplying 900 cubic metres of water every day so that the 17,000 GWI anchors can be drilled into the cofferdams.

For the Amstelveen bypass, Van Schaik is placing more than 80,000 cubic metres of EPS.

80,000 cubic metres of EPS

While we’re on the subject of numbers: in addition to the earthworks for the Amstelveen bypass, Van Schaik is placing more than 80,000 cubic metres of EPS at four bridges. “EPS is ideal because it is lightweight, around a hundred times lighter than sand, and therefore puts less load on the subsoil.” Van Schaik is also supplying concrete approach slabs for various structures, 411 in total. These slabs provide a smooth transition between the road and the bridge. They help prevent settlement and level differences that can arise from ground movement and traffic loading.

Van Schaik carried out all the sewer works on Keizer Karelweg.

Racing against the clock

One of the challenges on this project is time. “You’re always racing against the clock. It amazes me every time that we still manage to get it done. For example, a weekend closure has to be requested from Rijkswaterstaat a year in advance. On average, we have 15 to 30 people working on the project each day, five days a week, as well as at least 20 weekends. You have to plan carefully. All the work has to fit together like a puzzle. Planning also takes a lot of time, which leaves less time for execution. The shorter the execution period, the more you depend on your people being available. If you then have to scale up, that is quite a challenge,” says Van Schaik.

Van Schaik has been brought in for major earthworks on the A9.

Calling on its network

For Van Schaik, the A9 is clearly a project of big numbers. “One day we’re working with water, the next on earthworks, then we’re installing a pipeline. No two days are the same.” Given the volume of work, the earthworks specialist is calling on its network of subcontractors. “For weekend works, we bring in extra equipment. We might have five mobile cranes, four tractors, two crawler cranes and four large wheel loaders on site. Fortunately, we have colleagues who are happy to lend a hand. A good network is very important. If you can’t share, you can’t multiply,” Van Schaik concludes.      

Een zakelijke vraag aan Van Schaik Grondverzet B.V.? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeMaterials and techniques for infrastructure
  • SubjectRoad construction
  • CompanyVan Schaik Grondverzet B.V.
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.