Unusual bridge swap makes Krúsrak bridge renovation unique

Text Suzanne van Gaale Images Dave van Schaik

Bovenaanzicht van het werkterrein met de stalen brug die de Krúsrak brug tijdelijk vervangt.
Bovenaanzicht van het werkterrein met de stalen brug die de Krúsrak brug tijdelijk vervangt.

Rijkswaterstaat is renovating the timber Krúsrak bridge over the N7 near Sneek this autumn. For the work, the entire bridge has been moved to a nearby worksite and replaced by a temporary steel bridge. Civiele technieken deBoer (CT deBoer), based in Nieuwegein, is jointly responsible for the temporary worksite and the ‘bridge swap’ on behalf of Rijkswaterstaat. “It was, and still is, like trying to fit a puzzle on a postage stamp,” says Roy Grieving, project manager at CT deBoer.

The Krúsrak bridge is a distinctive structure made entirely from sustainable Accoya wood. However, an inspection found cracks in the Accoya wood, and its protective coating is also peeling off. A major renovation was needed. The project ‘N7 maintenance, Krúsrak bridge’ reached its first milestone last May: the bridge swap. After months of preparation, two bridges were moved over the course of a single weekend. The Krúsrak bridge was relocated to the worksite on Selfhelpweg, where it is being renovated. A temporary steel bridge, suitable for cars, cyclists and pedestrians, was installed in its place. “We had previously used this temporary modular bridge on the A16,” says Grieving. “We adapted the design to fit the existing structure and meet Rijkswaterstaat’s requirements.”

The bridge was transported to the worksite on SPMTs (self-propelled modular transporters).

Span over water

CT deBoer also set up the temporary worksite. This involved more than installing fencing, access points for transport vehicles and steel road plates. Temporary foundations also had to be prepared. Because of the clay soil, the piles were driven more than 20 metres into the ground. “The worksite itself measures 70 by 35 metres. That sounds large, but once we had assembled the temporary bridge here, it was like trying to fit a puzzle on a postage stamp. There is also a canal between the N7 and the worksite. To transport the bridges across the water, we also prepared a temporary crossing with a 25-metre span.”

Expertise

CT deBoer worked with Wagenborg Nedlift on the transport. The company also installed the original bridge in 2008. “We work together regularly and make a great team. We also often lend each other equipment. Because we know each other well, the bridge swap went smoothly.” To move the Krúsrak bridge, it was first jacked up. Wagenborg Nedlift was then able to move it from its position and transport it to the worksite on SPMTs (self-propelled modular transporters). “The temporary steel bridge travelled the route in reverse. When we installed it, we had only 4 centimetres of clearance. That certainly called for considerable expertise. To ensure the bridge connected properly to the existing structure, despite a height difference of 28 centimetres, the height of the two access roads was adjusted and they were connected to the temporary bridge with asphalt.”

If the renovation stays on schedule, the Krúsrak bridge will be moved back into place in early 2026 and will be able to serve for decades to come.     

Question about this story? Ask your question

Who worked on Krúsrak brug

  1. construction consortiumHWO (Hupkes Wijma & Koninklijke Oosterhof Holman)Mentioned in Krúsrak bridge: carefully managed renovation and smart contract split
  2. construction consortiumHWO construction consortiumMentioned in Krúsrak bridge renovation: controlled drying process in purpose-built shed
  3. clientRijkswaterstaatMentioned in Krúsrak bridge renovation: controlled drying process in purpose-built shed
  4. transportWagenborg NedliftIn this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectKrúsrak brug
  • ThemeMaterials and techniques for infrastructure
  • SubjectBridge construction
  • CompanyWagenborg Nedlift
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.