Major project in the Vlaketunnel
Text Roel van Gils Image Jennissen

12,000 m² of asphalt ripped in record time
The Vlaketunnel in Zeeland was fully closed to traffic for ten days in April for major maintenance. During this period, a new asphalt layer was laid, among other works. To make this possible, Jennissen removed the asphalt from both tunnel tubes in record time. No fewer than seven rippers were used simultaneously, with SAES International brought in to help.
Working for Gebr. Van Kessel, Jennissen was responsible for removing the asphalt in the Vlaketunnel down to the concrete. The 8-centimetre-thick asphalt layer covered a total area of around 12,000 m2. Heavy machinery was brought in to tackle this major project: no fewer than seven excavators equipped with rippers, supported by a wheel loader and an additional excavator at the storage area. The asphalt slabs produced were taken away immediately.

Five new rippers
Jennissen initially had three rippers, but these proved insufficient for a project on this scale. The company therefore turned to SAES. In a short time, SAES built five rippers tailored entirely to Jennissen’s requirements. “This enabled us to rip with seven excavators at the same time, significantly boosting productivity,” says project manager Pieter Pels. The results speak for themselves: in two 16-hour shifts, 6,000 m2 of asphalt was removed each time. “We started on the first tunnel tube on Thursday, and the contractor was able to lay new asphalt in that tube again on Saturday,” Pels explains. “Work on the second tunnel tube, in the direction from Zeeland to Brabant, started on Monday. This job was also completed within sixteen hours, allowing the new asphalt layer to be laid in this tube two days later.”

Excellent service
The partnership with SAES once again proved highly valuable. The company had previously supplied two rippers and various other attachments, and this time too, it responded quickly. “They provide excellent service,” says Pels, who also praises SAES for its flexibility and accessibility, as well as its ability to respond quickly to specific customer requirements. As well as purchasing equipment, all five rippers were bought by Jennissen, the company also regularly uses SAES’s hire service. “We recently hired a hydraulic breaker for a project in Maasbree,” says Pels. “It was delivered in excellent condition to the project site, with a technician there to adjust it (including fine-tuning). We got the most out of it, as the breaker performed optimally throughout the project.”
Jennissen’s work in the Vlaketunnel was part of a larger ten-day operation, which also included work on the expansion joints and replacement of the crash barriers, alongside the asphalt resurfacing. Looking ahead, Pels expects large-scale projects of this kind to become more common. “Investing in the five rippers was a strategic decision,” he says. “The successful completion of the work in the Vlaketunnel shows what can be achieved with the right preparation and the right people and partners around us.”
Een zakelijke vraag aan Saes International BV? Get in touch
Who worked on it
Vlaketunnel
- rippers
SAES International - removing the asphaltJennissen
Keep following this
Get an email when a new story is published. No account needed.
- ProjectVlaketunnel
- ThemeExtending the life of roads and civil engineering structures
- SubjectMachines & equipment
- CompanySaes International BV
- CompanyJennissen