The Amstelveen line is being upgraded, and it is badly needed. The line has been in service in virtually its current form since 1990 and has grown into an important link in regional public transport. But the light rail vehicles are ageing, do not run frequently enough and are prone to breakdowns.

Safety around the line is also less than ideal. Light rail service 51 is therefore being converted into a safe, fast and reliable connection terminating at Amsterdam Zuid. Preparatory work for the conversion of the Amstelveen line has been under way for some time.

Foundation work gets under way
The symbolic start took place on 1 February, marking the beginning of construction work. The main contractor for the upgrade of this tram line is VITAL, a joint venture between VolkerWessels companies Van Hattum en Blankevoort, VolkerRail and KWS. It has now started work on the foundations. VITAL has engaged Kandt Aannemings- en Funderingsbedrijf BV for this work. With more than 40 years’ experience installing and removing sheet piles and pile systems in a wide range of locations and conditions, Kandt proved to be the right contractor for the job.

Ernst van Gelder, directeur van GVG Oliehandel.

Kandt is working simultaneously at several locations in Amstelveen, using multiple machines.

Marco Kandt says several of the company’s machines are at work. “We have started installing steel sheet piles. The work is being carried out with due consideration for the adjacent metro line, road and surrounding area. We want to minimise disruption as much as possible. The sheet piles are therefore being installed with minimal vibration using HF/VM vibration and, in part, without vibration using silent piling. The LeKa grout injection piles are installed entirely without vibration. This is particularly important for the three underpasses we are building. These three junctions are being converted to grade-separated crossings and lowered below ground level. Our equipment is currently spread across several locations along the Amstelveen line. Our added value lies in taking the logistical burden off the client in this complex challenge, where construction sites are very restricted and unforeseen circumstances are common. Our organisation and equipment are well suited to this.”

Het merk Agealube is inmiddels een gerenommeerde naam in de infrasector, niet alleen voor ‘reguliere’ smeermiddelen, maar ook voor ‘groene’

Work at Zonnestein station on Sportlaan.

A surprising approach
“On a large-scale urban project like this, it is important to carefully select the equipment to be used. You also encounter a lot of underground infrastructure that is not always visible beforehand. This means you have to adjust the schedule almost every day. We work closely with the client so that we can quickly adapt our operations. This agile collaboration with the client is working very well. We are also working simultaneously at several locations with multiple machines, which helps us significantly shorten the construction period. In that respect, too, disruption to local residents and passengers during construction will be less than expected. In addition to installing the sheet piles and piles, we also fit the steelwork to the sheet piles so that excavation can be carried out safely: the so-called bracing frames. We also carry out this welding and structural work.”

Amstelveenlijn

Kronenburg station in Amstelveen.

New machine
“At the end of last year, we invested in a new leader rig. This latest addition to our fleet can use a range of techniques and is being deployed on this project with a so-called top press, which can install or remove sheet piles without vibration. This means we are fully prepared for the future and ready to take on any project,” Kandt concludes.  

A business enquiry for Kandt Aannemings- en Funderingsbedrijf BV? Get in touch

Who worked on Amstelveenlijn

  1. Sheet piling and drilling rigsKandt Aannemings- en FunderingsbedrijfMentioned in Kandt Aannemings- en Funderingsbedrijf gets to work with multiple sheet piling and drilling rigs
  2. main contractorVITALMentioned in A range of disciplines involved in the Amstelveenlijn renewal

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectAmstelveenlijn
  • ThemeUnderground construction
  • SubjectBouwMat
  • CompanyKandt Aannemings- en Funderingsbedrijf BV
  • CompanyKWS
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.