Underground infrastructure

Station area renewal is a square-metre puzzle | De Entree

Station area renewal is a square-metre puzzle | De Entree

Almost everything is being overhauled and completely renewed: all road surfacing, tram infrastructure, jetties, quays, public lighting, traffic signals, cables and pipes, and the tree layout. Iv-Infra, a multidisciplinary engineering consultancy, is responsible for the integrated design of the De Entree project. But how do you bring all the plans together in one integrated design in this busy area, where every square metre is a puzzle, while allowing everyday life to carry on as normal?

Amsterdam’s busiest spot
The project area on the city-centre side of Amsterdam Centraal is one of the busiest places in the city. Everything converges here: pedestrians, cyclists, trains, trams, the metro, buses, sightseeing boats and coaches. Every day, 300,000 people pass through, and more than 1,300 tram services depart. With over 600 cables and pipes, foundations and metro tunnels, it is just as busy underground as above ground. The biggest challenges in renewing De Entree are fitting all the individual components into the overall scheme and managing the many interfaces. 

Designing without surprises
We want no surprises: not during construction, not for the municipality at project handover, and not in relation to agreed commitments. Designing without surprises is a guiding principle throughout the entire design process. As the site leaves no room for improvisation, the team opted for a ‘foolproof design’, deliberately favouring traditional, proven solutions. To prevent clashes during construction, every single project component was designed in 3D and then ‘virtually built’ in a 4D BIM model.

Mapping the existing environment
With every square metre of the area presenting a puzzle, it is essential to know exactly what the existing situation looks like in order to fit everything in properly and avoid clashes. What is located where, and what are the dimensions of every element in the area? Many changes over the years meant that drawings were often inaccurate. At the start of the project, the entire project area was scanned. The bridges in the area have been modified several times in recent years, making the available asset data unreliable in some cases. To ensure that the integrated design could be properly fitted to the existing structures, Iv-Infra also used 3D laser scanning from the water to map the bridges.

The integrated design
Iv-Infra is responsible for the entire integrated design for this project. This covers the design of the surface layout and road infrastructure, the remodelling of Stationsplein, modifications to the bridges and quays, and the structural design of the new cycle parking facility. It also includes integrating the rail infrastructure, drainage, cables and pipes, traffic signal systems and tram overhead lines. The new cycle parking facility will be built beneath the water, with an underground link between it and the new metro concourse at the central station to be built at a later stage. Iv-Infra produced the structural design for the cycle parking facility, working closely with wUrck, which designed its architecture, and GEO2 Engineering, which dealt with the geotechnical issues and designed the foundation and cofferdam. 

Smart design solutions
The entire tram infrastructure on Prins Hendrikkade and Stationsplein is being renewed, from the tracks, points, point controls and overhead lines to the tram stops themselves. GVB had already designed the tram alignment. This design determined the road infrastructure layout. Iv-Infra developed the tram design further in 3D, making it possible to identify any potential clashes with other elements in the area and adapt the design accordingly. 

Several bridges lead from Stationsplein into the city centre. The central access bridge, opposite the Victoria hotel, is being widened. To minimise risk, a traditional structural solution was chosen. The bridge is being widened using precast beams, which keep its underside level with that of the existing bridge. As a result, the widening will not be visible once complete, and the navigational clearance will remain unchanged. 

Prins Hendrikkade forms part of the flood defences protecting Amsterdam city centre.       
The new cycle parking facility will be built within these flood defences. In consultation with the water authority, it was decided to keep the flood defences functionally separate from the cycle parking facility. The replacement flood defence will be built as an anchored sheet-pile wall. Structurally, this wall will not form part of the facility. This design solution means that the cycle parking structure does not have to be treated as part of the flood defences, simplifying the permit process as well. During construction, the replacement flood defence will form part of the cofferdam. The cycle parking facility was also designed in 3D, allowing the team to verify that it would not affect existing structures, such as the piles beneath the neighbouring bridges and the anchors of the existing quay.

wUrck

Artist’s impression of the new cycle parking facility.

Managing interfaces
With so many different disciplines and stakeholders involved in the project, managing interfaces is the key design challenge. A targeted approach was adopted. To deliver the final design within the tight timeframe, the team began with a requirements clash analysis with the Municipality of Amsterdam. Together, we scrutinised all the requirements and used context diagrams to identify the design interfaces. Planning interfaces between the different design tasks were then established through lean sessions. As the final design was developed, it was coordinated with the various interface stakeholders. Specific control measures were agreed for each identified interface. Their implementation is monitored through the systems engineering tool in Relatics. Regular coordination meetings were also held to discuss technical matters. 

Completion of the final design was conditional on all interfaces being under control. This was ensured through internal reviews and clash detection using the combined 3D BIM models. The current detailed design phase is also subject to continuous checks against the integrated final design, to ensure that interfaces remain under control.  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeFlood protection and climate-resilient water management
  • SubjectUnderground infrastructure
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.