Preventing unacceptable electromagnetic interference with underground cables and pipelines?

Het EMC-team, van links naar rechts: Marjolein, Rik, Remco, Francine en Eric.
Het EMC-team, van links naar rechts: Marjolein, Rik, Remco, Francine en Eric.

EMC stands for electromagnetic compatibility. If a product is compatible, different electrical and electronic products can function alongside one another without loss of performance. EMC requirements have been drawn up to prevent EMC problems. These requirements also apply to underground cables and pipelines. This article takes a closer look at the NEN 3654 standard, which covers the effects of high-voltage connections on pipelines. 

SGS Roos+Bijl, part of SGS Nederland, specialises in underground infrastructure. It designs technical cable and pipeline networks for distribution and transmission, and oversees the installation, diversion and removal of cables and pipelines. These projects are often preceded by specialist calculations, including interference calculations. We spoke to two specialists in this field: Project Manager Remco van der Wel and Engineer Eric Lorsheijd.

NEN 3654

SGS Roos+Bijl carries out interference calculations in accordance with the NEN 3654 standard. Remco explains: “The standard covers the mutual effects of pipelines and high-voltage systems. High-voltage systems include high-voltage cables and overhead lines. Under the standard, low voltage is defined as up to 1000 volts (1 kV). Above 1000 volts (1 kV) is high voltage. NEN 3654 primarily describes how to determine whether pipelines and high-voltage systems have an adverse effect on one another in terms of safety and corrosion.” The standard sets out several steps to be followed. Both electrical and thermal interference are assessed.

Power cables in a trench.

Electromagnetic field

“A steel pipeline can become energised by a parallel high-voltage connection as a result of the electromagnetic field,” says Eric. “This electrical interference can lead to unsafe situations, because touch voltages may occur, or nearby installations and pipelines may be damaged by AC corrosion.” Remco adds: “The greater the length of the parallel section, and the shorter the distance between the pipeline and the high-voltage connection, the greater the adverse effect on the pipeline.

For example, an electromagnetic field extends more than 1 km on either side of a 10 kV high-voltage connection. If pipelines run parallel to the cable connection within this area, they may be adversely affected. The assessment takes account of the magnitude of the electrical and thermal interference and its consequences. “That is why it is so important to carry out interference calculations in advance. This prevents unpleasant surprises. Interference calculations do not apply to just one trench, but to the entire zone in which a high-voltage connection could cause interference,” says Remco.

Heat generation

Eric says: “Another problem that can arise from underground high-voltage cables is heat generation. This heat can cause thermal damage to pipelines near the high-voltage connection. The rise in soil temperature can damage a pipeline through increased coating degradation, a higher corrosion rate and thermal stresses. The transported medium can also be affected, for example by bacterial growth.”

Detailed calculations

A number of factors are established before the calculations are made. Eric lists them: “You need to know the soil profile and soil resistivity. Is a pipeline coated or not? If so, what is the coating made of? What material is the pipeline made from? The distance between the cable connection and the outside of the pipeline is important, as is the length of the parallel section.” Remco adds: “We obtain a lot of information from the cable operator. We find out how deep the high-voltage cable is, whether the cables are laid flat or in a triangular arrangement, the cable length, voltage, current, short-circuit current and disconnection time.” A great deal of information is therefore needed from the cable and pipeline operators. Eric says: “Working in accordance with the NEN standard means starting the investigation broadly and working through the various steps to see what comes out at the bottom of the ‘funnel’. This requires detailed calculations.”

Eric: “We obtain a lot of information from the cable operator. We find out how deep the high-voltage cable is, whether the cables are laid flat or in a triangular arrangement, the cable length, voltage, current, short-circuit current and disconnection time.”

Simulating the pipeline system

One of the steps is to map and simulate the pipeline network. “This also takes account of existing connections, insulating joints and drainage systems, for example,” Remco explains. “We assess the maximum permissible voltage on the pipeline. We also consider whether the existing situation could change as a result of new cables being installed. We request this information from the relevant pipeline owners. They also check the calculations before physical work can begin. More and more pipeline owners require an interference calculation in advance.”

Energy transition

The energy transition is driving increased demand for interference calculations. “Our team is busier than ever with this work. Our clients are diverse and include network operators, pipeline owners, contractors, solar farm owners and wind farms. We now receive requests from all kinds of organisations to carry out calculations for them. Existing networks are also being expanded, while some electricity networks are due for replacement. In these cases too, it must first be demonstrated that the change will not cause adverse interference. This can be done by carrying out an interference calculation. Even if only part of an existing connection is being replaced, the situation must be assessed again,” says Remco. Eric concludes: “We are in constant contact with pipeline owners so that we can carry out our calculations as accurately as possible.”     

Question about this story? Ask your question

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeUnderground construction
  • SubjectUnderground infrastructure
  • CompanyRoos Groep
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.