Heinenoordtunnel first tunnel in South Holland to be renovated

Text Susan PeekImage Rijkswaterstaat, Nick Franken, Syb van Breda & Co architects

Heinenoordtunnel first tunnel in South Holland to be renovated

as part of Rijkswaterstaat’s major renovation programme

The Netherlands is facing a huge infrastructure maintenance challenge. Over the coming years, more than a hundred bridges, tunnels, locks and viaducts will be renovated on behalf of Rijkswaterstaat. The Heinenoordtunnel is the first of eight tunnels in South Holland to be renovated. Construction consortium Savera III, comprising Dura Vermeer, SWARCO (formerly Dynniq) and SPIE Nederland, is responsible for carrying out the renovation and developing the new tunnel automation system.

Construction consortium Savera III built a mock-up of part of the tunnel wall with the central tunnel duct. (Image: Nick Franken)

Sustainability drive

The road surface will be renewed and the concrete repaired, among other works. As part of the sustainability measures, the tunnel walls will be made lighter in colour, reducing the need for supplementary lighting. This will lower energy consumption. New light fittings and LED lighting will also be installed. A central tunnel duct will be added to house the new tunnel automation system. The old systems will remain in operation until the new systems have been installed, tested and approved. After the renovation, this central tunnel duct will serve as the new escape route. The existing service buildings will also be refurbished and given a new appearance so that they blend in better with their surroundings.

Rick Schreurs, technical manager at SPIE. (Image: Nick Franken)

Multitechnical service provider

SPIE Nederland is a subsidiary of the SPIE Group, Europe’s leading independent multitechnical service provider in the fields of energy and communications. SPIE Nederland supports its clients in the design, implementation, operation and maintenance of a range of installations in the energy, infrastructure, industrial and building sectors. “As the largest multitechnical service provider in the country, we are keen to take a leading role and contribute to a future-proof Netherlands,” says Rick Schreurs, technical manager at SPIE. Schreurs has worked at SPIE for ten years across various divisions and is ultimately responsible for the design and testing phase of the Heinenoordtunnel Renovation project. “In effect, I’m the technical conscience of my colleague Jurgen van den Bos, who has worked at SPIE for 21 years and is also a member of the management team in the traffic and transport department.” Van den Bos is SPIE’s project manager for the Heinenoordtunnel Renovation project. “Together with SWARCO, SPIE is responsible for designing, installing, testing and maintaining the tunnel technical installations.”

Jurgen van den Bos, project manager at SPIE. (Image: Nick Franken)

Technical solutions to technical challenges

“We design, install and maintain the power supply, the mechanical installations, such as the liquid pumping system, the fire-fighting system, the ventilation and pressurisation systems, and the building services installations,” says Van den Bos. “In addition to these installations, SPIE is also taking care of the emergency doors and emergency station cabinets.” Schreurs explains that building the new installations in parallel while the old ones are still operating is a considerable challenge. “The power supply needs to be able to handle twice as much, and you also have to consider the space available. The new cable route must not obstruct the old one, and there is limited space for the new system. An intensive preparatory phase was needed to ensure everything ran smoothly. Using a mock-up built by Savera III of part of the tunnel wall with the central tunnel duct, we were able to identify the technical challenges in advance and devise solutions.” 

Good cooperation is essential to the success of this project. According to SPIE, cooperation is excellent both within the consortium and with Rijkswaterstaat. (Image: Nick Franken)

Tight schedule

Alongside the technical challenges, the tight schedule also requires serious consideration. “The entire project, from the mechanical works to the renovation of the tunnel technical installations, will be carried out in several phases over a total of forty nights, thirty weekends and two summer periods,” says Van den Bos. “That means having the right people and materials in the right place at the right time, so that we do not jeopardise the project duration and can meet the schedule.” Schreurs explains that this phased approach means the existing systems remain operational until the new systems have been installed and tested. “This avoids the need to close the tunnel for months, keeping disruption relatively limited for the more than 110,000 road users who travel through it each day. It also gives us certainty that everything is working properly before switching from the old systems to the new ones.”

The phased approach means the existing systems remain operational until the new systems have been installed and tested. This keeps disruption to a minimum. (Image: Nick Franken)

Good cooperation

Good cooperation is essential to the success of this project. “And it is going excellently, both within the consortium and with Rijkswaterstaat,” confirms Van den Bos. “At SPIE, we work according to the One-SPIE philosophy: there is so much expertise across SPIE’s various departments and disciplines that it is put to full use on projects like this. This strong foundation increases the value we offer clients and ensures we are ready for even more large-scale infrastructure projects. 

Een zakelijke vraag aan SPIE Nederland B.V. – Smart city? Get in touch

Who worked on it

Heinenoordtunnel, renovation

  1. tunnel systemsSPIE Nederland
  2. Savera III construction consortiumDura Vermeer
  3. tunnel automationSWARCO

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectHeinenoordtunnel
  • ThemeExtending the life of roads and civil engineering structures
  • SubjectUnderground infrastructure
  • CompanySPIE Nederland B.V. – Smart city
  • CompanyDura Vermeer
  • CompanySWARCO
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.