Building the Stationsplein cycle parking facility is a logistical tour de force

Building the Stationsplein cycle parking facility is a logistical tour de force

We take a look at a construction site in the heart of Amsterdam. I follow the work taking place in the excavation for the cycle parking facility via a YouTube livestream, while my interviewee has a view of the work from the window of the site office.

I am speaking to Maarten Struijs, project manager for the cycle parking facility at Max Bögl & Partners. “Have you noticed how neat and orderly everything looks?” he asks. I have to agree. “The biggest challenge in building this cycle parking facility is working in a confined space. By managing the logistics intelligently and making the most of the space we do have, everything runs smoothly and we cause as little disruption as possible.”

De video laadt pas als je op afspelen klikt.

The construction site boundary is a tramway

“Fully 75% of the space just outside our site consists of tram tracks. That means there is no room on those sides for deliveries, removals or storage. So there is precious little space left, but we are good at making the most of it. That calls for solutions that are a little different from the norm,” Maarten continues. “Transport and logistics have to be kept as compact as possible. We bring in most materials by ship, unloading them within reach of our tower crane. Much as people did in the past, and it makes perfect sense when you consider how much water there is in Amsterdam. A welcome added benefit, of course, is that deliveries by water cause less disruption anyway. No impact on city traffic, no noise nuisance and lower CO2 emissions.”

The construction site is surrounded by tram tracks.

Maarten enjoys the view over the excavation: “It never gets old. I have been working on projects in Amsterdam city centre since 2003, so I am used to working in confined spaces. The cycle parking project, though, is a real test of that. It helps enormously that our experience means we know what the municipality of Amsterdam wants and requires. That gives us peace of mind and avoids unnecessary back-and-forth. We also know the city like the back of our hand, which means we can be creative in tackling logistical challenges. ‘Nothing beats experience’, as they say.” The team led by Maarten is called CIA, or Constructies, Installatie en Afbouw. “The sheet piling was installed by our partner Beens Groep. The underwater concrete and dewatering are part of CIA’s remit.”     

Maarten Struijs, project manager for the cycle parking facility at Max Bögl.

From 3D model to reality

Maarten and his team are wholeheartedly committed to the project. “I enjoy every phase. We have known what we are building now for a long time, thanks to the 3D model. You start with nothing and gradually see something take shape, see what was presented virtually become reality. That gives you quite a buzz,” Maarten explains. At the time of the interview, the columns are being installed and the final reinforcement is being placed. “The last floor section has also been cast. Work on the walls and columns is now under way. A 80 cm-thick concrete floor has been laid on top of the underwater concrete floor, forming part of the building’s enclosed structure. A formwork structure will then be built on the columns to cast eleven roof sections. They will all be cast in situ.”

‘Teamwork makes the dream work’, even in the excavation.

Our own storage and transhipment hub

Max Bögl & Partners has its own storage yard in the Western Docklands, a logistics hub of its own. It is near the hub operated by tugboat company Blom. Maarten says: “This hub allows us to transport as much as possible by water. Once again, no traffic jams, no traffic disruption, virtually no nuisance to the surrounding area and lower CO2 emissions. For me, the big advantage is that I can schedule ‘just in time’ deliveries much more effectively, both for incoming and outgoing goods. That gives us peace of mind and a clear overview, with a noticeable positive effect on the construction work. Ready-mixed concrete is delivered by road, as unfortunately there is no alternative (yet). The pumps are on Prins Hendrikkade, on the west side, with a pumping line running beneath the road into the excavation. We are constantly looking for ways to work smarter, and it is paying off. Instead of cramming the limited space with storage, we make clever use of alternative logistics, and everything is well under control.”

Work on the walls.

Future developments at the entrance

The focus is now on the floors, followed by the walls. “Once those are complete, it will be time for the roof. The quay structure for sightseeing boats will also be built then. The entrance area to the facility is still being developed, with sloping channels for the moving walkways. These will have a gradient of 11 degrees, providing access to the cycle parking facility. That is a tour de force in itself. Once the roof is closed, we will focus on the facility’s services and substructure. Then the cycle racks will go in and the glass walls will be installed. Installatietechniek Louwer from Oudewater is responsible for the electrical and mechanical services. Schindler is supplying the moving walkways and escalators, while Nederlandse Natuursteen Industrie is supplying the natural stone for the finishing work. The glass façades are from Interior Glassolutions.”

At the time of the interview, the columns are being installed and the final reinforcement is being placed.

‘Teamwork makes the dream work’

Maarten speaks matter-of-factly about the calm and steady progress of the project, but recognises that this is quite exceptional. “How do I see it? It is nothing new for us. In various roles at Max Bögl, I have had to tackle this kind of challenge before. This project is also running smoothly. The secret is mainly good planning, drawing on experience, starting to work out solutions to problems in good time and… bringing together the perfect combination of partners. That last point is hugely important and is also one of Max Bögl’s strengths. Every member of Max Bögl & Partners has been selected against carefully drawn-up criteria. We simply leave nothing to chance. Communication plays a key role in our line of work, that much is clear. Teamwork makes the dream work!”

We have known what we are building now for a long time, thanks to the 3D model.

Concrete from our own factory

To work quickly and efficiently while maintaining quality, Max Bögl sources the concrete columns from its own factory in Hamminkeln, Germany. “That is just across the border, near Emmerich,” Maarten explains. “This allows us to guarantee quality and keep costs under control. Our principle is that if we can do something well ourselves, we do it ourselves. If others can do it better, we bring them into the project as partners. The tower crane on site is ours too. We have a large fleet of our own plant and equipment, which includes this rail-mounted tower crane.”

COVID-19 restrictions made it a real challenge to get staff to the construction site and keep them there.

Maarten looks across the excavation once more and sighs: “It is lovely that everything is progressing in such an orderly way. But the pandemic has brought new challenges. Some of our staff do not live in the Netherlands. Travel restrictions and additional laws and regulations have made it a real challenge to get people to the construction site and keep them there. The same applies to deliveries from abroad and the 1.5-metre distancing measures. Having ten people take a break together in a site caravan was suddenly out of the question, of course. By working in fixed pairs and teams, setting maximum occupancy limits, restricting visitors and expanding the facilities in the site office, we have managed the effects and avoided a shutdown. It is still impossible to predict what the current and future measures will mean for the schedule and delivery. We are all extremely proud of this project, and that makes the atmosphere between us more than good.”     

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeUnderground construction
  • SubjectUnderground infrastructure
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.