Amsterdam | De Entree

The entire area on the city-centre side of Amsterdam Centraal is being redesigned. More space for pedestrians and cyclists, more water and, above all, fewer cars. The area from the station building to Damrak and from Schreierstoren to Westertoegang is being comprehensively redeveloped over a period of around five years. Project manager Joost Beljon of Max Bögl & Partners describes the project as one big logistical puzzle, with the major works carried out in successive phases to preserve the functionality of the area as far as possible.
One big logistical puzzle
Main contractor Max Bögl has an interesting philosophy on how the project should be delivered. “As well as building the new structures, this is above all a major transformation that we are organising on site,” says Beljon. “That is why, from the tender stage onwards, we have brought in specialist partners, working together as one team to deliver the project. To illustrate, their input ranges from advice on mobility, geotechnical engineering and design to contractors renewing the cables and pipelines. It was a deliberate choice, but an essential one to ensure the success of a project involving so many different disciplines.”
Westertoegang and changes to the main routes
The area around the central station is extremely busy, both on land and on the water. Nevertheless, the entire area is being completely redeveloped to improve its spatial quality and connection with the city. More space is being provided for cyclists and pedestrians, and less for motor traffic. The project has been divided into phases to minimise disruption to the surrounding area. Beljon: “In the first half of 2018, we began by redeveloping and lowering Westertoegang to create the so-called ‘cut’, meaning through traffic now travels behind the station. The area in front of the station has been made low-traffic. The municipality changed the main routes at the same time as the Noord/Zuidlijn began operating, on 22 July 2018. That also meant we had a firm deadline for opening Westertoegang. The new public transport plan also came into effect at that point, and various bus and tram routes were changed. The design, permitting and work preparation for the entire Westertoegang sub-area were therefore brought forward so it could open on time. And we succeeded.”
Underground cycle parking
In the phasing puzzle, Westertoegang and the changes to the main routes were therefore an important step, Beljon recalls. “Moving the motor traffic also created the space needed to relocate cables and pipelines and renew the road infrastructure ahead of construction of the underground cycle parking facility. We are currently also building the so-called Cuyperstrap between the central station hall (Cuypershal) and the metro hall. This is being done using a unique freezing technique, a specialism of Max Bögl. The new stairs will allow passengers to transfer between train and metro, and vice versa, entirely indoors. We are therefore creating an additional underground connection, reducing the number of pedestrians in the station square. This will free up space to redevelop the entire station square. The challenge of building here is not so much the schedule or complex structures, but above all ensuring that the area remains operational during the works. The ferry companies have meanwhile already moved to a temporary location, and work is under way to relocate cables and pipelines so that construction of the cycle parking facility can go ahead.”

Opening Westertoegang on time was an important step in the phasing puzzle (Image: Richard Mouw).
Construction of the cycle parking facility began in April. Beljon: “The facility is being built in a construction pit and will provide space for 7,000 bicycles on a single level, at around 7 metres below NAP. There will be water above the facility, even more than there is now. That will bring a sense of calm to this busy area.” In the coming years, cycle parking spaces will also be created elsewhere on the station island. This will allow all bicycles to be parked out of sight in future, and all the bicycle racks can eventually be removed from the area. In due course, the cycle parking facility will have an underground connection to the metro hall.
Max Bögl & Partners
The partners of main contractor Max Bögl are:
- Count & Cooper
- Knipscheer Infrastructuur
- Beens Groep
- Iv-Infra
- Akson
- GEO2 Engineering
- wUrck
- Goudappel Coffeng
- Kummler+Matter
- Alom
- Van den Heuvel Heesch
- Installatie Techniek Louwer
De Entree project
The area on the city-centre side of Amsterdam Centraal is being redeveloped. The entire area is being redesigned, with more greenery, more space for pedestrians and cyclists, and more water. An underground cycle parking facility for 7,000 bicycles will be built beneath the water. All tram stops and tracks are also being renewed. The De Entree project will connect with the Rode Loper, the above-ground area of the Noord/Zuidlijn, which has already been completely redeveloped. Work to redesign the station area began in early 2018 and will take around five years.
A business enquiry for Count & Cooper? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeFlood protection and climate-resilient water management
- SubjectUnderground infrastructure
- CompanyCount & Cooper
- CompanywUrck architectuur stedenbouw landschap
- CompanyVan den Heuvel