A web of cables and pipes | De Entree

Infrastructure construction starts below ground. This is certainly true of the De Entree Amsterdam project, where a veritable web of cables and pipes lies underground. As a consultancy specialising in underground cables and pipes, Akson makes this extensive network clear and easy to understand. It is no surprise, then, that the engineering consultancy has been involved in the project since the tender in 2016.
“After the contract was awarded, we were brought in as a partner because of the proven added value we could offer,” says Bram van de Vondervoort, cables and pipes coordinator at Akson. “At that point, as an engineering consultancy, we began selecting a combined contractor and identifying the interfaces, possible solutions and phasing for the first phase, De Westertoegang. This proved to be quite a task, and we were grateful to work successfully with contractor Van den Heuvel from Heesch. The density of cables and pipes underground was such that clearing the ground for the planned concrete underpass at Westertoegang was a complex job, both on paper and during construction. Extensive consultation and coordination with the other project partners resulted in a detailed design for the first sub-area. After the necessary preparation and coordination with the various network operators, we started work on 8 January 2018. Once the cables and pipes had been rerouted and the pavement had, figuratively speaking, been founded on cables and pipes, Max Bögl and partner Knipscheer could also begin redesigning the above-ground infrastructure.”

After the necessary preparation and coordination with the various network operators, we started work on 8 January 2018. (Image: Mees van den Ekart Fotografie)
The next phase is now also well under way, with coordination requirements having increased further, says Van de Vondervoort. “Akson’s original scope was to coordinate with and inform the network operators. Our current work has expanded to include drawing up plans, preparing the work and supervising its execution. Every day, we coordinate and optimise, among other things, designs for the tram’s power supply cables (traction power cables), Liander and Waternet cables and pipes, and soon also partial designs such as CCTV and cable routes for various connections to the structures (the cycle parking facility, temporary jetties for canal boats, etc.). We are closely involved with the community team and support contract management in dealing with changes and deviations. At Akson, we represent the interests of the cables and pipes on behalf of both the network operators and the civil engineering contractors. All in all, it is a very interesting project, involving many disciplines and offering valuable insights.”
As well as the De Entree Amsterdam project, Akson, a specialist engineering consultancy for underground cables and pipes, is or has been involved in work on projects including the A1-A6 widening between Diemen and Almere, strengthening the Waddenzeedijk Texel dyke, the Hoekse Lijn between Schiedam and Hoek van Holland, and Zuidasdok.

Extensive consultation and coordination with the other project partners resulted in a detailed design for the first sub-area. (Image: Mees van den Ekart Fotografie)
Have a business enquiry for Van den Heuvel? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeFlood protection and climate-resilient water management
- SubjectUnderground infrastructure
- CompanyVan den Heuvel