Safeguarding a drinking water transmission main

Waterschap Hunze en Aa’s is upgrading the embankment, banks and flood defences along the Afwateringskanaal van Duurswold. A new access road is also being built, directly over a substantial concrete drinking water transmission main (DN700) belonging to Waterbedrijf Groningen. To prevent the main from failing under the preload for the new access road, GW Leidingtechniek BV was called in to help.
Waterbedrijf Groningen’s drinking water network crosses the Afwateringskanaal van Duurswold at two locations near Tjuchem. “For a long time, the water company relied solely on the concrete drinking water transmission main, which passes beneath the canal as a siphon. However, looking to the future, a bypass was created a few years ago using a steel pipe installed by HDD beneath the canal,” says Harm van Ganzenwinkel, director of GW Leidingtechniek. “Until recently, both transmission mains were in service, but work on the drainage canal, and especially the construction of the new access road, changed that. The poor ground conditions on site, in the middle of the former Slochteren gas field, made it necessary to apply a preload to the ground surface. The weight could cause the old concrete main to fail.” This was reason enough for the water company to take action.

Installation of DN 700 mm steel main
GW Leidingtechniek’s scope of work included disconnecting the existing concrete transmission main and extending the steel HDD-installed section beyond the access road. “We had to complete all of this within a very tight five-week timeframe, right in the middle of the summer holidays, and across land owned by several different people. Good engagement with the local community was therefore essential. But you can leave that to us, as we have demonstrated time and again,” stresses Van Ganzenwinkel. “We held the discussions with landowners at their kitchen tables ourselves, explained what we were going to do and involved the local community fully in the plans. Work on site began with disconnecting the steel main, allowing us to extend the existing bore by around 100 metres on both sides. The steel pipes were unloaded, transported to the site and laid out beside the trench to be excavated. The pipes were then welded together. The welds were inspected using radiography and coated internally. Externally, the joints were wrapped in PE coating. After the dewatering system was installed, the trench was excavated, the pipes were lowered into it, and several field welds were made, inspected, coated internally and wrapped externally. The main was then pressure-tested at 8 bar. After passing the pressure and strength tests, it was approved for use. Following the pressure test, the main was flushed, with samples taken continuously until the required water quality was achieved. We call this point the bacteriological commissioning of the main.”

GRP insulating coupling
After bacteriological commissioning, GW Leidingtechniek had a maximum of 48 hours to connect the new main to the concrete transmission main at the north and south ends. “At both ends, we also installed a valve assembly with flushing facilities and the option to shut off the main,” adds Van Ganzenwinkel. “All in all, it was a substantial intervention, but everything went according to plan. The new steel main was connected to the concrete transmission main using a GRP insulating coupling with cast-iron fittings, including access openings and flushing points. Once the mains were connected, the concrete pipe beneath the Afwateringskanaal could be taken out of service. We then removed the concrete main on the north side as far as the siphon, including the old valve assembly. On the south side, the old concrete pipe was disconnected from the siphon in the flood defence, partially removed and sealed with grout.”
GW Leidingtechniek completed the project on time, despite work being postponed because of the hot summer weather. “A project like this, under time pressure, involving numerous stakeholders and carried out in the middle of the hot summer holidays, shows what we as a company are capable of. Another great reference and a satisfied client,” concludes Van Ganzenwinkel.
Een zakelijke vraag aan GW Leidingtechniek BV? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeFlood protection and climate-resilient water management
- SubjectYearbook
- CompanyGW Leidingtechniek BV