Thinking outside the box to ensure safety

Text Susan PeekImage Joeri Klink

BUKO Infrasupport treft alle verkeersvoorzieningen om de nieuwe aansluiting van Wezep en bedrijvenpark H2O op de A28 te kunnen realiseren.
BUKO Infrasupport treft alle verkeersvoorzieningen om de nieuwe aansluiting van Wezep en bedrijvenpark H2O op de A28 te kunnen realiseren.

when adapting the road network around Wezep

At the request of the Province of Gelderland, work is under way on a new connection between Wezep and business park H2O and the A28. The project is being carried out by main contractor Gebr. Van der Lee. BUKO Infrasupport is installing all the traffic management measures needed to deliver the new connection.

“It is quite unusual that the province opted for a RAW specification for this project instead of a standard tender,” says Robin Koelewijn, Project Manager, Traffic Management, North East Region at BUKO Infrasupport. “That meant we needed to prepare thoroughly and find out as much as possible about the project in advance, before the specification went out to tender.”

Safety

“As BUKO Infrasupport, we play only a small part in a project of this scale, but it is a very important one,” Koelewijn continues. “BUKO was chosen because we score highly on safety. We also actively contribute ideas for project-specific solutions and communicate very effectively, including when setting out the safety case.”

By raising awareness in advance and fostering understanding during the works, you can maximise safety for both the people working on site and road users.

A solutions-focused approach

“As with any project, there are challenges here that call for thinking outside the box to ensure safety.” Koelewijn cites the safety barrier. “As soon as you attach a screening panel to it, it loses its type approval. Yet both a screening panel and the barrier are requirements under the specification and CROW guidelines. So we came up with a project-specific solution: temporary fencing along the asphalt, fitted with opaque screening mesh. It meets all the requirements: traffic is not distracted by the works and can pass safely and without disruption. It is not only the safest option, but also cheaper than the original plan. That is quite exceptional, of course!” BUKO also came up with a solution for the barrier: “An emergency refuge had to be incorporated, and an emergency access point was needed because this is a busy interchange. We therefore recommended installing two runs instead of one. The straight run is positioned alongside the work zone, while the second starts behind the barrier. This creates a gap that can serve as an emergency access point.”

Understanding is crucial

In addition to devising project-specific solutions, BUKO is working hard to keep traffic informed both before the project and during the works. “It is astonishing how much information you need to provide at an interchange like this, and from so many different directions,” says Koelewijn. “But raising awareness beforehand and fostering understanding during the works can save lives. So during the weekend closure, we use DRIPs (dynamic route information panels), while temporary diversion routes and mobile message signs are positioned alongside the road to inform traffic accurately and in good time. These traffic management measures are also recorded in Melvin, the system that allows local authorities, emergency services and incident response teams to see where works are taking place and coordinate their activities effectively.”

Traffic management measures like these, implemented systematically, maximise safety for both the people working on site and road users passing the works. “And let’s not forget the people who install and remove the traffic management measures.” Koelewijn concludes by thanking contractor Gebr. Van der Lee: “For the pleasant cooperation and the trust they have placed in BUKO.”   

A business enquiry for BUKO Infrasupport? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectSafety
  • CompanyBUKO Infrasupport
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.