Hybrid piling at the Port of Antwerp with an electrified powerhouse

Text Roel van GilsImage Vroom Funderingstechnieken

Gezien de vele partijen en vele machines die tegelijk actief zijn op een relatief smalle strook, is een goede afstemming en coördinatie cruciaal voor de voortgang van het project.
Gezien de vele partijen en vele machines die tegelijk actief zijn op een relatief smalle strook, is een goede afstemming en coördinatie cruciaal voor de voortgang van het project.

Container ships are getting bigger, so quays must grow to match. The Port of Antwerp and container operator PSA Antwerp are therefore set to completely redevelop the Europa Terminal on the right bank of the Scheldt, with the environment firmly in mind. The aim is ultimately to halve CO2 emissions per container. Vroom Funderingstechnieken is already making a significant contribution, deploying its hybrid Hillcon HSCX1500GLS-E piling rig.

Vroom Funderingstechnieken is a familiar name in the Belgian market.

The redevelopment of the Europa Terminal supports the ambition of the Port of Antwerp and the container operators to make the best possible use of the existing space. It will also enable the port to accommodate ships with a greater draught in future. To achieve this, the existing 1,200-metre-long quay wall is being replaced, and the navigation channel is being deepened from 13.5 metres to approximately 17.5 metres. “Given the scale of the project and the fact that the existing terminal must remain operational, the work has been divided into three phases,” says Paul Bochem, account manager at Vroom Funderingstechnieken. “We have been commissioned to carry out the first, northern section by the TM Europaterminal Civiel consortium, comprising Artes Roegiers, Artes Depret and Herbosch-Kiere.”

20,397 metres

Vroom Funderingstechnieken is a familiar name in the Belgian market. “We are known here as specialists in more complex displacement piling,” says Paul. “For example, we founded the hospital in Liège on vibro piles and have delivered numerous wind turbine foundations. That expertise has also brought us to this project. We have been commissioned to complete the first section, which involves driving 709 piles with a total length of 20,397 metres.” Vroom Funderingstechnieken received the contract in late January 2023. “The timing worked out perfectly, coinciding with the delivery of our first hybrid piling rig. It was as if it had been meant to be, given Port of Antwerp’s sustainability ambitions. A great challenge, then, for our new electrified powerhouse.”

Vibro piles

The new quay wall is being built using a combi-wall, steel MV piles and vibro piles supplied by Vroom Funderingstechnieken. “These are vibro piles with a diameter of 559 mm and a 680 mm base,” explains Martijn Steenstra, project manager at Vroom Funderingstechnieken. “They are installed at an angle so they can transfer horizontal forces into the ground. With so many contractors and machines working at the same time along a relatively narrow strip, effective coordination is crucial to keeping the project on schedule.” That has not stopped Vroom Funderingstechnieken from deploying its hybrid piling rig here for the first time. “It may be a new machine, but it has been extensively tested and simulated beforehand. Of course, we may encounter a few teething problems, but the entire team from Hillcon and Vroom’s plant department will be on standby to make sure everything runs smoothly.”

150-tonne pulling force

According to Martijn, the Hillcon HSCX1500GLS-E is unlike a conventional piling rig. “The machine can both drive piles and drill, using displacement methods in both cases, and it is controlled by software and electronics. It is a whole new world for our operator, too. The hybrid machine also stands out for its enormous pulling force of 150 tonnes,” says Martijn. Paul concludes: “We took delivery of the machine on 12 May this year, after which it was transported to the Port of Antwerp. It is the biggest investment in Vroom Funderingstechnieken’s more than 60-year history. A second Hillcon HSCX1500GLS-E is currently under construction and will be ready for work from the first quarter of 2024. As a forward-thinking player in the piling market, we continue to invest as we work towards an emissions-free construction site.”   

Een zakelijke vraag aan Vroom Funderingstechnieken B.V.? Get in touch

Who worked on Europa Terminal

  1. piling worksVroom FunderingstechniekenIn this story
  2. demolition hammerSAESMentioned in High-tech precision work in fast-flowing water
  3. demolition companyAdex GroepMentioned in High-tech precision work in fast-flowing water
  4. GPS and laser systemCT SystemsMentioned in High-tech precision work in fast-flowing water

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectEuropa Terminal
  • ThemeUnderground construction
  • SubjectFoundations / Site investigation
  • CompanyVroom Funderingstechnieken B.V.