‘Working as an integrated project team should be standard practice’

Bij de Stevinsluizen worden in een zeer kort tijdsbestek de bestaande sluisdeuren gerenoveerd.
Bij de Stevinsluizen worden in een zeer kort tijdsbestek de bestaande sluisdeuren gerenoveerd.

In a unique partnership, Solidd Steel Structures worked with construction consortium Levvel (BAM, Van Oord, Rebel and Invesis) to deliver the vessel impact protection for the new navigation lock at Den Oever, commissioned by Rijkswaterstaat. It is a project that feels like a perfect fit for the Frisian company. 

A robust project management approach

The vessel impact protection for the new navigation lock was complex in every respect.

Although Solidd Steel Structures specialises in heavy steel construction, director Jan Willem Stob sees the company’s added value primarily in mechanical engineering structures. More specifically, in managing complex projects. “The more complex the assignment, the more enthusiastic we become,” says Stob. As part of the Afsluitdijk upgrade, the company is involved in four areas: overhauling the Stevin locks, delivering the stoplogs for the Fish Migration River, providing the drives for the river’s barrier gates, and, finally, the vessel impact protection for the new navigation lock at Den Oever. “Each assignment presents its own challenge. At the Stevin locks, for example, we had to lift out, assess and refurbish the existing lock gates within a very tight timeframe. Success depends on a robust project management approach, which suits us perfectly and plays to our strengths.”

Complex in every respect

The vessel impact protection for the new navigation lock was complex in every respect, technically, in terms of schedule and in terms of quality. “We tackled it as an integrated project team with Levvel. Because we have engineers with practical expertise on our team, we produce working drawings that can also be implemented efficiently on site. We optimised the design with Levvel, taking the lead in the process. A functional design was developed in a short time, with managing all the interfaces and areas of overlap being essential.”

A great way to work together

According to Stob, working as an integrated project team has significant benefits: “You make full use of everyone’s strengths, and costs and returns are completely transparent. The focus is on the technical side and delivery, because you agree the details in advance. Working as an integrated project team also calls for a different approach to how team members work together. Soft skills need a great deal of attention. Team members must trust one another and be able to work together seamlessly. As well as having the necessary technical expertise, it is also about the human side. That is exactly where Solidd wants to stand out: it is about who we are!”

Just around the corner

Working on the Afsluitdijk upgrade is especially meaningful for the Solidd team because the dike is ‘just around the corner’. “It is a high-profile project that everyone knows. The Afsluitdijk is essentially one large mechanical engineering structure designed to manage water, traffic, flora and fauna. We are incredibly proud to be able to contribute to it.”   

Question about this story? Ask your question

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeViable projects and strong collaboration
  • SubjectNews
  • CompanyVan Oord
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.