Two-phase procurement

Vlnr: Edwin van Dijk, Andre Ubink, Lenneke Muller, Robert-Jan Kwaak en Thomas Rijs.
Vlnr: Edwin van Dijk, Andre Ubink, Lenneke Muller, Robert-Jan Kwaak en Thomas Rijs.

Major infrastructure projects procured under a UAV-GC contract have by now become almost notorious. More often than not, they make the headlines. Examples include Zuidasdok in Amsterdam, the A15 Maasvlakte-Vaanplein and the Zeesluis IJmuiden. Mckinsey wrote a critical report on the subject, which led to Rijkswaterstaat’s report ‘Future Challenges for Rijkswaterstaat: Perspectives on the challenges and opportunities for improvement in the civil engineering, road and hydraulic engineering sector’. To turn the tide, Rijkswaterstaat announced a transition based on four measures. One of the measures announced is the so-called ‘two-phase process’. 

Rijkswaterstaat’s variants

Two-phase process

An important feature of a two-phase process is that the parties only agree prices for high-risk elements once those risks can be assessed more accurately. This reflects the widely held view that many problems stem from having to set a price at a point when much is still uncertain or unclear, namely during the procurement process. Professor of construction law at TU Delft, Prof. Dr M.A.B. Chao-Duivis, described this in her valedictory address as the biggest pain point of integrated contracts. Rijkswaterstaat has since also published an action plan: ‘Towards a resilient infrastructure sector: action plan, a starting point for a joint transition process’. Rijkswaterstaat has subsequently begun trialling this type of two-phase process on various projects. 

Phased price formation prevents a price from being set while much is still unclear.

Variants of the two-phase process

Rijkswaterstaat’s trials have resulted in several variants. One involves carrying out the two-phase process during the procurement procedure. It works as follows: the procurement procedure results in the selection of one party, while the price remains unset and the contract is not yet definitively awarded. This party then carries out the design phase (phase 1). This therefore takes place during the procurement procedure. The party is then the only one permitted to submit a tender. If the parties reach agreement, the contract is definitively awarded (phase 2, the construction phase).    

Another variant involves running a full procurement procedure with multiple parties. The contract is definitively awarded to the winner without a fixed price having been set. An agreement covering phases 1 and 2 is concluded with the winner. In phase 1, the design is developed, after which the client and contractor negotiate the price on a one-to-one basis. If they reach agreement, the project proceeds to construction (phase 2). If the parties cannot agree on a price, they can part ways. This is therefore also known as the ‘exit model’. This variant was used, for example, for the renovation of the Maastunnel in Rotterdam.

There is also an ‘entry model’. This is largely similar to the exit model, except that following the procurement procedure, an agreement is concluded only for phase 1 (design). If the parties then agree on a price, they enter into an agreement for phase 2 (construction). This model has been used, for example, on various dike reinforcement projects.  

Findings

Involving the contractor during the design process has advantages, because they can bring their construction expertise to bear when design choices are made. Involvement in the design, with the prospect of a contract for the construction phase, also encourages collaboration between the parties. This is evident, for example, from the experience gained with construction team agreements. Finally, phased price formation prevents a price from being set while much is still unclear. This has, after all, proved to be a recipe for disaster. 

One challenge is whether this new approach fits within the framework of procurement law. In any case, both clients and contractors appear to have much to gain from this two-phase process. It would be an illusion to think that this will put an end to problems on major infrastructure projects, but it is certainly a step in the right direction.   

R.J. Kwaak, lawyer at Construct Advocaten 

Question about this story? Ask your question

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeViable projects and strong collaboration
  • SubjectNews
  • CompanyConstruct Advocaten
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.