Tilting weirs: the heart valves of the peak storage basin

To control the flow of water into the basin, the inlet structure at Piekberging Haarlemmermeer is fitted with four stainless steel tilting weirs made by Kwaliteit Waterbeheersing Techniek (KWT). Because of their position in a regional flood defence, they effectively act as the heart valves of the peak storage basin and meet the second-highest execution class. KWT is part of Bergschenhoek Groep, a family business that has been in existence for more than 100 years and operates entirely carbon neutral, with 100% CO2 neutrality.

Under the Dutch Water Act, an opening through a regional flood defence must be fitted with a double defence. “The inlet structure at Piekberging Haarlemmermeer consists of a stoplog as the primary defence, followed by two pairs of tilting weirs in the inlet structure,” explains Andries van de Wal, sales manager at KWT. “The tilting weirs are normally always set at 90 degrees, in the closed position. When an emergency arises, which calculations indicate will happen once every fifteen years, the stoplog structure is removed and the tilting weirs open to an angle of 15 degrees, allowing the peak storage basin to fill in a controlled way.”
Structural safety
A tilting weir is a typically Dutch product that has been used for decades as a water level control system, with water gently trickling over it. At Piekberging Haarlemmermeer, however, the weirs have a different role. “They are not here to manage water levels, but to let in a very large volume of water as a movable flood defence for emergency management. The forces increase exponentially,” says Van de Wal. “A specific opening angle of 15 degrees was chosen. Why? It creates a particular hydrological balance, with very little vacuum effect at the inlet from the tunnel to the storage basin, allowing water to flow into the inlet culvert very efficiently at 2 x 7.5 m3 per second. But it has to work! Hoogheemraadschap van Rijnland was therefore determined that we should be able to guarantee structural safety in accordance with Rijkswaterstaat guidelines, as well as the specific opening angle. That is something we can certainly deliver.” At a flow of 7.5 m3 of water per second, more than 8,000 kilograms press down on the weir leaf. These are enormous forces at this leaf angle. Considerable attention was paid to structural safety because of the very stringent requirements, which are almost ‘nuclear’ in scale. “As KWT, we are not only qualified for this work, but certified too. At every point in the design and in every weld, we had to demonstrate that the stress in the material does not exceed 200 N per mm2. This is supported by a range of inspections, including X-rays. Hoogheemraadschap van Rijnland also engaged independent welding inspectors to inspect our welds. We always welcome that. We also have to meet all the additional structural safety factors set out in Rijkswaterstaat’s Richtlijn Ontwerp Kunstwerken 2.0. The design report alone runs to 178 pages, demonstrating that the KWT solution meets the requirements for this primary flood defence. This makes the tilting weir, this heart valve, a highly engineered structure.”
As a weir specialist, KWT always delivers bespoke solutions. The Haarlemmermeer project is no exception. “The zoning plan required the entire structure to remain below a specified threshold height,” says Van de Wal. “The permit was based on that. A ‘standard’ tilting weir design would have been 1 metre higher, which was not an option here. We therefore moved the drive mechanism to a separate chamber, among other measures, to keep the structure as compact as possible in terms of height.” Given the stringent quality requirements, KWT is also responsible for installing the four tilting weirs. “Our client wants to leave absolutely no room for risk in this area either.”
Een zakelijke vraag aan Nederlands Instituut voor de Bouw? Get in touch
Who worked on Piekberging Haarlemmermeer
- tilting weirsKwaliteit Waterbeheersing Techniek (KWT)In this story
- clientHoogheemraadschap van RijnlandIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectPiekberging Haarlemmermeer
- SubjectNews
- CompanyKwaliteit Waterbeheersing Techniek (KWT)
- CompanyHoogheemraadschap van Rijnland
- CompanyNederlands Instituut voor de Bouw