The final piece

To ensure people can continue to live safely and healthily in the Rijnland water management area, which lies up to several metres below NAP, the regional water system must function properly. Around the turn of the millennium, an extensive study was carried out into how the Rijnland regional water system functioned and how resilient it would be in the future. The study found that additional pumping and storage capacity would be needed to keep the system robust in the years ahead. This prompted Hoogheemraadschap van Rijnland to take action. The study identified three measures that would restore the regional water system to the required level. Piekberging Haarlemmermeer is the final piece.

Climate change means we are increasingly experiencing heavy and prolonged rainfall. This can lead to significant flooding in a short space of time. “Most of the Rijnland region lies below sea level, so we need to ensure that excess water can be collected and then pumped away,” says Jos de Wilde, environment manager at Hoogheemraadschap van Rijnland. “We pump water from our polders into the regional water system, a connected network of waterways in the area. From there, pumping stations move it to open water: the North Sea, Hollandse IJssel and the North Sea Canal. Flooding occurs when water cannot flow to these pumping stations quickly enough, or when they reach their limits and can no longer cope with the huge volumes. The regional water system is then at risk, potentially causing flooding in cities such as Leiden and Haarlem, while the entire bulb-growing area could literally end up under water.”

Pressure relief valve
To restore the regional water system to the required level, Hoogheemraadschap van Rijnland is investing in three projects. Two have already been completed. “The capacity of the Katwijk pumping station has been substantially increased to around 100 m3 per second,” says Lodewijk Biemond, project manager at Hoogheemraadschap van Rijnland. “We have also built Piekberging De Nieuwe Driemanspolder near Zoetermeer, providing a temporary buffer for 2 million cubic metres of water. And work is now being completed on Piekberging Haarlemmermeer, with a capacity of 1 million cubic metres. These measures take the strain off the regional water system.” Think of the two peak storage areas as a kind of pressure relief valve in our system, ensuring that excess water can be regulated and stored temporarily, adds De Wilde. “Climate change has only increased the urgency and the need for these measures in recent years, and we do not expect that trend to stop. We are already seeing extreme conditions that models had not predicted until much later. However, based on the latest KNMI models and climate scenarios, we expect to use the peak storage area once every fifteen years.”

Balanced earthworks
After the zoning plan was amended many years ago, Hoogheemraadschap van Rijnland had already purchased the land for Piekberging Haarlemmermeer. “The location and boundaries of the peak storage area had therefore already been established,” says Biemond. “We also set the requirements ahead of the project. The storage area must be able to fill within 24 hours and be emptied again within five days. We also gave the consortium some freedom in the design so that we could make good use of the expertise available in the market.”
Piekberging Haarlemmermeer will operate entirely by gravity. No pumps are needed to bring the peak storage area into operation or to empty it. De Wilde says: “With the MEAT tender criteria, we placed considerable emphasis on sustainability and CO2 reduction. The contractor chose to carry out the work with a balanced earthworks approach. The contractor surveyed the entire area in great detail to allocate the soil across the dike sections. As a result, almost no soil was transported on public roads.”
Work is progressing well. “I think everyone involved is proud to be contributing to this project,” says De Wilde. “The atmosphere on site is good, and there is also a lot of interest from the local community, with positive feedback. The consortium deserves praise for the way it involves local residents in the project. There is also a great deal of interest beyond the immediate area. We regularly organise tours and site visits because this project clearly demonstrates, in a nutshell, the role of Hoogheemraadschap van Rijnland and the impact of climate change on life below sea level.” For this reason, Piekberging Haarlemmermeer was also in the spotlight recently at the thirteenth National Delta Congress.
Question about this story? Ask your question
Who worked on Piekberging Haarlemmermeer
- tilting weirsKwaliteit Waterbeheersing Techniek (KWT)Mentioned in Tilting weirs: the heart valves of the peak storage basin
- clientHoogheemraadschap van RijnlandMentioned in Tilting weirs: the heart valves of the peak storage basin
Keep following this
Get an email when a new story is published. No account needed.
- ProjectPiekberging Haarlemmermeer
- SubjectNews
















