Fail to warn, and you may pay dearly.

The law imposes a number of duties to warn on contractors. Breaching a duty to warn can prove costly for a contractor.
Breaching a duty to warn can lead to liability and disputes on a construction project, outcomes all parties involved would prefer to avoid. In this article, Construct Advocaten discusses a number of duties to warn.
The general duty to warn
The starting point is that the client is responsible for the brief. As a result, errors in specifications, drawings or construction instructions supplied by the client are generally at the client's risk. This is the general rule, since the contractor's duty to warn can shift that responsibility to the contractor.
The contractor is required to warn the client about the errors mentioned above, insofar as the contractor knew or ought reasonably to have known about them. The contractor's expertise plays an important role here: the more specialist knowledge the contractor has, the sooner they can be expected to spot an error.
Breaching the duty to warn makes the contractor liable for any resulting damage. Another possible consequence is that a claim for additional work may be rejected if that work could have been avoided by a timely warning.

Additional work
The contractor also has a duty to warn in cases of additional work. Additional work arises when the client requests additions to or changes in the agreed work. In principle, the contractor is entitled to an increase in the price only if they have informed the client in good time that the changes will result in a price increase.
Case law shows that this duty to warn is subject to fairly stringent requirements. Before carrying out additional work, the contractor must give the client as realistic an estimate as possible of the specific additional costs expected. If they fail to do so, the contractor cannot claim an increase in the price.
Target price
Where the parties agree a target price, the law stipulates that it may not be exceeded by more than 10%. Here too, the exception is if the contractor has warned the client of such an overrun. If they fail to do so, they cannot charge for the excess. Case law includes cases in which contractors have even had to repay amounts already received.
Cost-increasing circumstances
Circumstances that increase costs may arise after the contract has been concluded. These are circumstances that the contractor did not allow for in the price and that are not attributable to them. They may justify an adjustment to the price of the work, provided the contractor did not have to take the possibility of such circumstances into account when setting the price.
Once again, the contractor is entitled to a price adjustment only if they have warned the client. In this case too, the contractor must give the warning before carrying out the work affected by the cost-increasing circumstances. The warning must also specify the extent of the cost increase.
Finally
Our advice is always to give warnings in writing. Make sure the warning is sufficiently specific and leaves no room for doubt. State what you are warning about and the consequences of what you have identified. Because those who take precautions do things right.
For more information, contact Construct Advocaten.
Question about this story? Ask your question
Companies in this story