Condition assessment of a bridge about which little is known

How do you deal with a bridge whose construction and structural condition are unknown, and whose current capacity may appear inadequate based on a visual assessment? What steps should you take, and how do you determine the right course of action? Is continued service a realistic option, or should strengthening or replacement be considered?
A step-by-step investigation
Bridge AK14 is on the Geesterweg, crossing the ‘Slikker Die’ in Akersloot, and is managed by BUCH (the municipalities of Bergen, Uitgeest, Castricum and Heiloo). The structure has a cast-in-situ deck with an integrated crossbeam supported at four points by concrete piles. It was widened by 3.25 metres on the eastern side, also using cast-in-situ concrete. Iv-Infra was commissioned by BUCH to investigate the bridge in stages, making the process cost-effective.

Step 1: Inspection and qualitative assessment
The condition of all components above ground level or the waterline was assessed. Limited destructive testing was used to determine whether carbonation and/or chlorides (mixed into the concrete) were present. Extensive concrete damage was observed on the underside of the deck and on the crossbeams. Where the concrete cover was missing, slight to moderate deterioration of the reinforcement was observed. Diagonal cracks were found in the crossbeams near the concrete piles, close to the repaired areas. Overall, the maintenance condition is moderate. The repairs observed were inadequate, and cracking in the crossbeams reduces their structural capacity.
In general, the carbonation front does not extend beyond the first layer of reinforcement. However, chloride levels in the old section of the deck exceed the limit (0.4% m/m of cement) at more than 50% of the test locations. Chlorides mixed into the concrete were ruled out. The geometry was also surveyed during the inspection.
On this basis, continued service is considered a realistic option. The bridge’s structural safety over the next 30 years must be established through recalculation.
Step 2: Further investigation
At a minimum, the verification calculation for the bridge deck requires data on its structural thickness, concrete strength class, reinforcement steel grade and reinforcement configuration. Iv-Infra established these details in just two days, using only a pontoon and scaffolding, so no traffic management measures were needed.
Concrete strength was determined by taking Ø100 mm concrete cores at locations agreed with the structural engineer. One of the drilling locations was also used to establish the actual structural depth locally. Three reinforcing bars were extracted from across the underside of the deck to determine the grade of reinforcement used. All test locations were reinstated, and the concrete cores and reinforcing bars were tested in a laboratory.
Ground-penetrating radar was used to map the reinforcement from the underside of the deck and crossbeams. The survey established which reinforcement was located at the top and bottom of the deck, whether the reinforcement was cranked near the supports, and whether additional reinforcement had been installed in the span. The exact bar diameter was then established through destructive testing.
The results of non-destructive mapping of the reinforcement configuration using ground-penetrating radar depend heavily on the conditions. At bridge AK14, the reinforcement was mapped with reasonable accuracy, except at a few difficult-to-access locations, such as where additional support reinforcement may have been installed.

Step 3: Verification calculation
The information gathered in Step 2 was used as input for the verification calculation. The bridge deck was modelled in the finite element analysis programme SCIA Engineer. The calculation included several conservative assumptions about the structural thickness of the entire deck and some of the top reinforcement.
The recalculation concluded that the deck’s capacity was insufficient to meet the strength requirements of the current standards. As the capacity was exceeded at a few specific locations, a brief literature review of comparable bridges was carried out. This suggested that more top reinforcement may be present at the supports than had been assumed conservatively. It was therefore recommended that this reinforcement be mapped after all. If additional reinforcement was indeed present, the bridge deck would meet the specified requirements.
Step 4: Investigation of top reinforcement and revision of the verification calculation
The assessment of the structural deck thickness had established that a levelling layer had been applied to the top of the deck. As the thickness of this layer and the asphalt was not known precisely, and destructive verification of the reinforcement diameter was required, it was decided to expose an area of approximately 0.5 by 0.5 metres near the support by removing the concrete. This was done using water jetting, a controlled method that does not damage the reinforcement. Once the reinforcement was exposed, the suspicion was confirmed: additional top reinforcement was present. This information was then incorporated into the verification calculation.
The revised verification calculation shows that the structure has sufficient capacity and therefore meets the strength requirements of the current standards. The calculation was based on the original condition, which means the damage must be repaired durably in the short term. In the meantime, a limited axle-load restriction of 45 tonnes gross vehicle weight was recommended to prevent further damage.

Step 5: Repair plan
Repair work is required to return the bridge to its original condition. Two CUR recommendations were used as guidelines in the repair plan: CUR Recommendation 118:2015 for repairing the concrete damage, and CUR Recommendation 119:2016 for crack injection. Given the large proportion of the deck underside affected, it was decided to renew the entire underside of the concrete deck. Two factors must be considered when determining the depth of concrete removal: the degree of bar corrosion and the thickness of the concrete cover. Exposed reinforcement must be cleaned in accordance with NEN-ERN ISO 8501-1. To maintain traffic, a method was devised to carry out the work in phases, allowing the bridge to remain open.
Step 6: Carrying out the repair work
The work on bridge AK14 has since been completed successfully, restoring the bridge to good condition.
The staged approach demonstrated structural safety in a targeted and cost-effective way and identified the maintenance required. With a well-considered plan of action, bridges in moderate condition can still meet structural requirements.
Question about this story? Ask your question
Who worked on it
Brug AK14 in Castricum
- onderzoekIv-Infra