Additional payment due to rising construction costs: what are the options?

Van links naar rechts: Edwin van Dijk, Andre Ubink, Lenneke Muller, Robert-Jan Kwaak en Thomas Rijs.
Van links naar rechts: Edwin van Dijk, Andre Ubink, Lenneke Muller, Robert-Jan Kwaak en Thomas Rijs.

Cobouw is full of reports about it. The prices of construction materials are soaring. At the time of writing, since January this year, prices for timber and sheet materials have risen by 20%, steel prices by as much as 77%, oil prices (relevant to the price of bitumen) by 36%, and copper prices by 31%.

Price rises are nothing new in themselves. For many years, the law, the UAV 2012 and the UAV-GC 2005 have all included provisions for cases involving substantial price rises. With price rises so much in the news, there is every reason to take a closer look at these provisions.

Cost-increasing circumstances

In the event of substantial price rises, both the law and the UAV 2012 give the contractor the right to (partial) reimbursement of these additional costs, provided certain conditions are met. The contractor must have been unable to foresee the price rises when entering into the construction contract, and the price rises must substantially increase the cost of the works.

In the past, when steel prices suddenly and unexpectedly rose sharply, contractors successfully invoked these so-called cost-increasing circumstances. Case law established, among other things, that neither a fixed-price clause nor a risk allocation scheme precludes a claim based on cost-increasing circumstances. These are deemed to relate to ‘normal’ price rises, but not to abnormal ones.

Substantiality requirement

A contractor can claim additional payment for cost-increasing circumstances only if the increase in costs is substantial. Unfortunately, there is no clear rule for determining when this is the case. A 2016 ruling by the Council of Arbitration for the Construction Industry appears to offer a rule of thumb: an increase of more than 5% of the total contract sum would be substantial. However, there is also case law rejecting such a rule of thumb. Whether the increase in costs is substantial depends on the circumstances of the case. This is an open-ended criterion and, unfortunately, offers little guidance in practice. 

Business risk

It should also be borne in mind that the Council of Arbitration always considers the extent to which the contractor should have allowed for a certain degree of price increases. This is known as business risk, the proportion of the increase in costs that the contractor must bear itself. Note that in the cases mentioned above concerning steel price rises, this risk was regularly set at between 10% and as much as 20% of the increase in costs. 

Unforeseen circumstances

Finally, the cost-increasing circumstances must have been unforeseen. This may be arguable for works contracted before the recent sharp price rises, although prices had already risen quite sharply after the credit crisis. It will be much harder to invoke the provisions mentioned above for works contracted now. In light of the sharp price rises of recent months, further increases may well be considered foreseeable. In that case, a claim based on cost-increasing circumstances will fail. 

Duty to warn

Both the law and the UAV 2012 require the contractor to warn the client of the cost-increasing circumstances as soon as possible. Failure to do so precludes a successful claim based on cost-increasing circumstances. The rationale behind this provision is that the client must be able to amend the order in order to limit costs.

UAV-GC 2005

Under the UAV-GC 2005, the contractor is entitled to reimbursement of costs if an unforeseen circumstance arises that is such that the contract cannot remain in force unchanged. The drafters of the UAV-GC drew on the statutory provisions governing unforeseen circumstances. This is generally considered to be a very strict test. Successful claims under this provision are virtually unheard of, and it is harder to meet than the test for invoking the so-called cost-increasing circumstances provisions in the law and the UAV 2012.

Finally

Successfully claiming additional payment due to rising construction costs is no easy matter. But the provisions in the law and the UAV 2012 are there for a reason, and contractors have successfully relied on them in the past. In the current climate, it may be worth checking whether the main requirements for a claim for additional payment are met.   

R.J. Kwaak, construction law solicitor at Construct Advocaten     

Question about this story? Ask your question

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeViable projects and strong collaboration
  • SubjectNews
  • CompanyConstruct Advocaten
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.